Expansion of existing Sponge iron/DRI From 90,000 to 1,25,000 TPA, Induction Furnace and Billet Caster from 2 x 12 T (300 TPD) to 1 x 12 T, 1 x 15 T (416 TPD), Captive Power Plant from 12 to 12.5 MW, addition of Hot Rolling Mill including galvanizing 425 TPD and Fly Ash Brick Manufacturing Unit 30 TPD to 40 TPD (i.e., 35000 Bricks/day, 7000 Blocks/day) by Goa Sponge & Power Limited

Expansion of existing Sponge iron/DRI From 90,000 to 1,25,000 TPA, Induction Furnace and Billet Caster from 2 x 12 T (300 TPD) to 1 x 12 T, 1 x 15 T (416 TPD), Captive Power Plant from 12 to 12.5 MW, addition of Hot Rolling Mill including galvanizing 425 TPD and Fly Ash Brick Manufacturing Unit 30 TPD to 40 TPD (i.e., 35000 Bricks/day, 7000 Blocks/day) by Goa Sponge & Power Limited is a lapsed industrial project in Santona, Sanguem, South Goa, Goa. The site covers 43.5 acres. Its stated project cost is ₹86.6 crore. As of 27 Nov 2026, its status is “Lapsed” (since 29 Oct 2024).

See it on the live map All projects in South Goa

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Expansion of existing Sponge iron/DRI From 90,000 to 1,25,000 TPA, Induction Furnace and Billet Caster from 2 x 12 T (300 TPD) to 1 x 12 T, 1 x 15 T (416 TPD), Captive Power Plant from 12 to 12.5 MW, addition of Hot Rolling Mill including galvanizing 425 TPD and Fly Ash Brick Manufacturing Unit 30 TPD to 40 TPD (i.e., 35000 Bricks/day, 7000 Blocks/day) by Goa Sponge & Power Limited is a lapsed industrial project in Santona, Sanguem, South Goa, Goa. The site covers 43.5 acres.

Who is building it?

The applicant is Goa Sponge and Power Limited.

Has it been approved?

No. The application was lapsed on 29 Oct 2024, so it is no longer under consideration.

Where is it?

In Santona, Sanguem, South Goa, Goa.

How big is it?

It has a stated cost of ₹86.6 crore and a site of 43.5 acres.

When was it filed?

The application was filed on 5 Jul 2023.

One of 3 filings for this project. The project's main page, with every filing and where each stands: Expansion of existing Sponge iron/DRI From 90,000 to 1,25,000 TPA, Induction Furnace and…

Project details

StatusLapsed
Status since29 Oct 2024
Application filed5 Jul 2023
Approval soughtEnvironmental approval
Application typeEarly planning
SectorIndustry
ApplicantGoa Sponge and Power Limited
Land area43.5 acres (17.6 ha)
Project cost₹86.6 crore
Village / localitySantona
Taluk / tehsilSanguem
DistrictSouth Goa
StateGoa
Location fromSite boundary on record
Our referenceWID-GA-00023

All filings for this project

This project has 3 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
Expansion filed 6 Jul 2023Environmental approval granted43.5 acres₹86.6 crore
Early planning filed 6 Jul 2023Lapsed43.5 acres₹86.6 crore
Early planning filed 5 Jul 2023 (this page)Lapsed43.5 acres₹86.6 crore

In context

12 applications in South Goa since January 2022 are in the same category (Industry): 6 approved, 4 filed or under review, and 2 withdrawn, lapsed or rejected. At 43.5 acres, this one is larger than 67% of them.

31 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Santona, Sanguem, South Goa, Goa. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

All 4 Goa Sponge and Power projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.