Lilo of One Ckt of Narendra(Existing)-Narendra(New) 400 KV D/C Quad Transmission Line is a power project in Darbandora, Dharbandora, South Goa, Goa. The site covers 221 acres.
Who is building it?
The applicant is Goa Tamnar Transmission Project Limited.
Has it been approved?
Yes. Its status is “Decision issued” (since 27 Oct 2023), as of 27 Nov 2026.
Where is it?
In Darbandora, Dharbandora, South Goa, Goa.
How big is it?
It has a stated cost of ₹50 crore and a site of 221 acres.
When was it filed?
The application was filed on 27 Oct 2023.
Project details
| Status | Decision issued |
|---|---|
| Status since | 27 Oct 2023 |
| Application filed | 27 Oct 2023 |
| Approval sought | Wildlife review |
| Application type | New project |
| Sector | Power |
| Applicant | Goa Tamnar Transmission Project Limited |
| Land area | 221 acres (89.4 ha) |
| Project cost | ₹50 crore |
| Village / locality | Darbandora |
| Taluk / tehsil | Dharbandora |
| District | South Goa |
| State | Goa |
| Location from | Site area on record |
| Our reference | WID-GA-00316 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 27 Oct 2023 (this page) | Decision issued | 221 acres | ₹50 crore |
| New project filed 15 Dec 2022 | More information requested | ₹50 crore |
In context
8 applications in South Goa since January 2022 are in the same category (Power): 2 approved, 4 filed or under review, and 0 withdrawn, lapsed or rejected.
Where it is
Darbandora, Dharbandora, South Goa, Goa. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Lilo of One Ckt of Narendra(Existing)-Narendra(New) 400 KV D/C Quad… — more information requested, 2 km away
- Iron Ore Beneficiation Plant — not approved, 5.2 km away
- Minrani Exports & Imports — lapsed, 5.3 km away
- Proposed Laterite Stone Quarry of Lease Area 2.58 Ha Located on land bearing… — environmental approval granted, 6.5 km away
- Development of Eco-Camps at Collem, South Goa — decision issued, 7.6 km away
- Proposed Laterite Stone Quarry with lease area 2 Ha located on land bearing… — environmental approval granted, 9.1 km away
- Handling of Iron Ore dump at Dump-97, Situated on private property at Survey… — initial checks, 10.1 km away
- Work of releasing of 1Ph power supply to 05nos. of applicants as per the new… — initial checks, 10.7 km away
More from Goa Tamnar Transmission Project Limited in South Goa
- 400 kV D/C Xeldem - Mapusa transmission line & Xeldem- Xeldem (Existing) 220… — forest land use approved
3 Goa Tamnar Transmission projects in South Goa
All 4 Goa Tamnar Transmission projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.