Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 26 Nov 2022 |
| Application filed | 26 Nov 2022 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Ganesh Empire |
| Land area | 1.3 acres (0.5 ha) |
| Project cost | ₹5.3 crore |
| Village / locality | Nikol |
| Taluk / tehsil | 0 |
| District | Ahmadabad |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-00169 |
What the filings say
What is planned
Ganesh Empire is a residential building project proposed by the applicant, Ganesh Empire, in Nikol, Ahmedabad. The project consists of four residential blocks (A, B, C, and D) with a total of 88 flats.
The building configuration includes two basement levels for parking, a ground floor or hollow plinth, and up to seven upper floors. Specifically, Block A is planned for seven floors, while Blocks B, C, and D are planned for six floors each.
Project Components
| Item | Detail |
|---|---|
| Total Plot Area | 0.53 hectares (1.31 acres) |
| Total Built-up Area | 26,690.51 square metres |
| Total FSI Area | 14,256.21 square metres |
| Residential Units | 88 flats |
| Number of Blocks | 4 |
| Maximum Floors | Basement (2) + Ground + 7 floors |
| Parking Capacity | 307 Equivalent Car Spaces (ECS) |
Layout and design
The site layout features a central 6.00-metre wide approach road that provides access to the four blocks. Blocks A and B are situated on one side of the approach road, while Blocks C and D are on the opposite side. The project includes two common plots, totaling 621.60 square metres.
Vertical circulation in each block is provided by two lifts and one staircase of 2.00 metres width. The design incorporates a dual plumbing system to separate fresh water from treated sewage used for flushing. For energy efficiency, the applicant proposes using LED lighting, solar power generation of 130 KW for common areas, and aerated blocks for construction.
Water, power and access
The total water requirement during the operation phase is estimated at 63.8 kilolitres per day (KLD). Of this, 43.1 KLD will be fresh water sourced from the Ahmedabad Municipal Corporation (AMC), and 20.7 KLD will be met through treated sewage for flushing and gardening.
Sewage generation is expected to be 47.6 KLD, which will be treated in an on-site Sewage Treatment Plant (STP). Approximately 26.9 KLD of treated wastewater will be discharged into the AMC drainage line.
Power will be sourced from the local grid, with a 125 KVA diesel generator set proposed for emergency backup. Access to the site is provided via 12.00-metre wide Town Planning Scheme (TPS) roads on two sides of the plot.
Environmental safeguards
The applicant plans to develop a greenbelt area of 955.2 square metres, which includes 133 trees. Rainwater harvesting will be managed through two percolation wells and a 50,000-litre underground storage tank.
Solid waste management involves source segregation into dry and wet waste. Organic waste will be treated on-site using an Organic Waste Converter (OWC), while recyclable materials will be sold to vendors. For fire safety, the project includes underground water storage tanks with a total capacity of 400 KL (four tanks of 100 KL each) and 20 KL terrace tanks for each block.
As part of Corporate Environment Responsibility (CER), the applicant has committed to sponsoring tree plantation on 5.5 hectares of community land and installing solar street lights and rainwater harvesting structures in Memadpur and Gatrad villages.
Ganesh Empire site plan and layout
A drawing from the project's filings. Sign in free to see it.
🔒 Sign in free to see itIn context
1,175 applications in Ahmadabad since January 2022 are in the same category (Buildings & townships): 916 approved, 201 filed or under review, and 58 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 1.3 acres, this one is smaller than 65% of them.
226 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Nikol, 0, Ahmadabad, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- The Vatican — environmental approval granted, 200 m away
- The Vatican — environmental approval granted, 200 m away
- The Vatican — environmental approval granted, 200 m away
- Atlantis — environmental approval granted, 350 m away
- Hindva Luxuria — under environmental review, 350 m away
- Building project by 'LIG House under PMAY' of Ahmedabad Municipal Corporation — environmental approval granted, 350 m away
- Building project by 'LIG House under PMAY' of Ahmedabad Municipal Corporation — lapsed, 350 m away
- Building project by 'LIG House under PMAY' of Ahmedabad Municipal Corporation — environmental approval granted, 350 m away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.