Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 30 Nov 2022 |
| Application filed | 30 Nov 2022 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Riseonic Infraspace LLP |
| Village / locality | Gota |
| Taluk / tehsil | Daskroi |
| District | Ahmadabad |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-00236 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 12 Dec 2024 | Environmental approval granted | 1.5 acres | ₹68.9 crore |
| New project filed 30 Nov 2022 (this page) | Environmental approval granted |
What the filings say
What is planned
RISEONIC INFRASPACE LLP proposes a mixed-use development consisting of three blocks, identified as Blocks A, B, and C. According to the environmental approval granted in March 2023, the project was initially approved for a structure comprising two basements, a ground floor, and 11 upper floors. The applicant's revised master plan indicates a proposed expansion to 13 upper floors.
The development is designed to accommodate both residential and commercial components. The approved plan includes 64 residential flats and 110 commercial units, which consist of shops and offices. Under the proposed expansion, the number of residential units would increase to 80 flats, bringing the total unit count to 190. The total built-up area for the approved project is 30,212.46 sq. m., with the expansion proposing an increase to 32,923.04 sq. m.
Layout and design
The project is located on a plot of 0.61 hectares (1.51 acres). The design features a common plot area of 764.05 sq. m. and a hollow plinth area for parking. The layout includes internal approach roads with widths of 6.00 metres. Parking is distributed across the two basement levels and the hollow plinth, utilizing a multilevel mechanical parking system to provide a total capacity of 307 cars.
| Item | Detail |
|---|---|
| Approved Built-up Area | 30,212.46 sq. m. |
| Proposed Expansion Area | 32,923.04 sq. m. |
| Approved Residential Units | 64 flats |
| Proposed Residential Units | 80 flats |
| Commercial Units | 110 shops and offices |
| Approved Floors | 11 floors |
| Proposed Floors | 13 floors |
| Parking Capacity | 307 cars |
| STP Capacity | 110 KLD |
| Solar Power Generation | 53 kW |
Water, power and access
The total water requirement during the operational phase is estimated at 125.35 KLD. The applicant's project report states that 64.48 KLD will be fresh water sourced from the Ahmedabad Municipal Corporation (AMC), while the remaining 60.87 KLD will be met through treated sewage. The project will generate approximately 60.87 KLD of sewage, which will be treated in an onsite Sewage Treatment Plant (STP) with a capacity of 110 KLD.
Power backup will be provided by a 100 KVA diesel generator set equipped with an acoustic enclosure. The site is accessible via separate entry and exit points on the adjoining approach road.
Environmental safeguards
The project includes a planned green belt area of 1,524.05 sq. m., which incorporates a tree-covered area of 760 sq. m. The applicant proposes to plant 152 trees within the premises. For water conservation, two percolation wells will be installed for rainwater harvesting from rooftop and paved areas.
Solid waste management will involve the segregation of waste at the source. Biodegradable waste will be treated in an onsite organic waste converter, while recyclable materials will be sold to authorized vendors. Energy-saving measures include the installation of a 53 kW solar power generation system, the use of LED lighting fixtures, and rooftop thermal insulation.
The Riseonic site plan and layout
4 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
1,175 applications in Ahmadabad since January 2022 are in the same category (Buildings & townships): 916 approved, 201 filed or under review, and 58 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval.
219 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Gota, Daskroi, Ahmadabad, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Terranova — environmental approval granted, 50 m away
- The Riseonic — environmental approval granted, 100 m away
- Parkview Bougainvillea — initial checks, 200 m away
- Aaryan Buildpro — environmental approval granted, 500 m away
- Aaryan Buildpro — environmental approval granted, 500 m away
- Crestville — environmental approval granted, 650 m away
- Shantam Parmeshwar — environmental approval granted, 650 m away
- Shantam Parmeshwar — environmental approval granted, 650 m away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.