Avadh Arkelia is an approved building project in Rundh, Majura, Surat, Gujarat. The site covers 3.5 acres.
Who is building it?
The applicant is Pioneer Construction Company.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 9 Nov 2023), as of 27 Nov 2026.
Where is it?
In Rundh, Majura, Surat, Gujarat.
How big is it?
It has a stated cost of ₹114.5 crore and a site of 3.5 acres.
When was it filed?
The application was filed on 9 Nov 2023.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 9 Nov 2023 |
| Application filed | 9 Nov 2023 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Buildings & townships |
| Applicant | Pioneer Construction Company |
| Land area | 3.5 acres (1.4 ha) |
| Project cost | ₹114.5 crore |
| Village / locality | Rundh |
| Taluk / tehsil | Majura |
| District | Surat |
| State | Gujarat |
| Location from | Site area on record |
| Our reference | WID-GJ-00489 |
What the filings say
What is planned
Pioneer Construction Company proposes to expand its commercial building project, Avadh Arkelia, in Surat. The applicant's project report states that the development will consist of a single commercial building divided into two blocks (Block A and Block B). The structure is planned to have three basement levels, a hollow plinth, and 11 floors, reaching an ultimate height of 42.49 metres.
The project is an expansion of a previously granted environmental clearance from September 2018. While the original plan envisioned a mall with 312 hotel rooms, restaurants, and a cinema, the revised proposal focuses on a commercial complex. It will house 507 commercial units, specifically 460 offices and 47 shops. The total built-up area is planned at 1,06,667.28 square metres on a plot of 14,040 square metres (approximately 3.47 acres).
| Item | Detail |
|---|---|
| Total Built-up Area | 1,06,667.28 sq. mt. |
| F.S.I. Area | 55,929.08 sq. mt. |
| Ground Coverage | 8,577.22 sq. mt. |
| Basement Area | 34,773.75 sq. mt. |
| Total Commercial Units | 507 (460 Offices, 47 Shops) |
| Building Height | 42.49 metres |
| Configuration | 3 Basements + Hollow Plinth + 11 Floors |
Layout and design
The layout includes designated areas for showrooms and offices with common utilities. The ground floor and hollow plinth are designed for parking and entrance foyers. The three basement levels are dedicated to parking and services. Block A and Block B are connected at the lower levels, with Block A being the larger component.
Designated parking space for 1,292 Equivalent Car Spaces (ECS) is proposed, exceeding the requirement of 1,119 ECS. This includes 1,073 spaces in the basement, 87 on the surface, 55 in the hollow plinth, and 77 on the first floor. The project also includes 258 electric vehicle charging points.
Land and surroundings
The project site is located at Block No. 23, O.P. No. 36, F.P. No. 36 in Rundh, Majura. The land is classified as private non-agricultural land. The site is approximately 4.15 km from Surat Airport and 9.78 km from the Surat railway station. National Highway 8 is located about 20.46 km to the east. The applicant states that no national parks or wildlife sanctuaries are within a 10 km radius.
Water, power and access
Water supply will be provided by the Surat Municipal Corporation (SMC). During the operation phase, the total water requirement is estimated at 104.6 kilolitres per day (KLD), of which 59.56 KLD will be fresh water and 45.04 KLD will be recycled treated water. Wastewater generation is expected to be 79.08 KLD, which will be treated in an on-site Sewage Treatment Plant (STP) with a capacity of 100 KLD using Moving Bed Biofilm Reactor (MBBR) technology.
Power will be sourced from Dakshin Gujarat Vij Company Limited (DGVCL) with a connected load of 2,700 kW and a maximum demand of 2,600 kW. For backup, three diesel generator sets of 125 kVA each are proposed. The project plans to utilize solar power for common area lighting, with 481 solar panels providing a capacity of 260 kW.
Environmental safeguards
The applicant proposes a green belt area of 1,500 square metres, which includes the planting of 351 trees such as Gulmohar, Jambu, and Limdo. For solid waste management, an Organic Waste Convertor (OWC) with a capacity of 250 kg/day will be installed to process organic waste into manure. Dry waste will be collected in bins and disposed of through the SMC system.
Rainwater harvesting will be implemented through four recharge wells. Energy conservation measures include the use of LED lighting, roof-top thermal insulation, and aerated blocks to reduce heat stress. The building will also feature a Building Management System (BMS) to monitor electrical, mechanical, and water supply utilities.
Timeline
The applicant's documents from November 2023 indicate that diaphragm wall work has already started at the site based on the previously granted environmental clearance. The total environmental management plan budget is ₹7.22 crore for capital expenditure and ₹23 lakh for annual recurring expenses.
Avadh Arkelia site plan and layout
4 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
489 applications in Surat since January 2022 are in the same category (Buildings & townships): 376 approved, 79 filed or under review, and 34 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 3.5 acres, this one is larger than 86% of them.
143 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Rundh, Majura, Surat, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Avadh Crestina — environmental approval granted, 200 m away
- Construction Project "Eco Capital" — environmental approval granted, 250 m away
- Construction Project "Eco Capital" — environmental approval granted, 250 m away
- Construction Project "Eco Capital" — environmental approval granted, 250 m away
- Proposed High-rise Residential Building Project (G+12) of "Avadh Martella"… — cleared for impact study, 250 m away
- Proposed High-rise Residential Building Project (G+12) of "Avadh Martella"… — environmental approval granted, 250 m away
- Residential Building Project by Bhawans Vanilla Ultima — environmental approval granted, 300 m away
- Rajhans Nexora — initial checks, 300 m away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.