Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 16 Nov 2023 |
| Application filed | 16 Nov 2023 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Shree Infracon Private Limited |
| Land area | 5.2 acres (2.1 ha) |
| Project cost | ₹209.2 crore |
| Village / locality | Vadaj |
| Taluk / tehsil | Sabarmati |
| District | Ahmadabad |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-00495 |
What the filings say
What is planned
Shree Infracon Private Limited, in collaboration with the Ahmedabad Municipal Corporation (AMC), proposes a residential building construction project under the Slum Rehabilitation Policy, 2013. The project is located at Nava Wadaj in the Sabarmati taluk of Ahmedabad.
The development is planned to consist of buildings with a maximum height of 24.85 metres, structured as a ground floor plus seven upper floors (GF + 7). The project will provide a total of 1,694 residential units.
According to the project description, the total built-up area is 90,819.82 square metres. The permissible Floor Space Index (FSI) area is 63,604.24 square metres, of which 60,950.15 square metres will be utilized. The ground floor built-up area is 11,161.12 square metres.
| Item | Detail |
|---|---|
| Total Units | 1,694 (Residential) |
| Building Configuration | Ground + 7 Floors |
| Maximum Height | 24.85 metres |
| Total Built-up Area | 90,819.82 square metres |
| Total Used FSI Area | 60,950.15 square metres |
| Proposed Parking Area | 8,290.27 square metres |
| Proposed Common Plot Area | 2,227.72 square metres |
| Planned Trees | 531 Nos. |
| Percolation Wells | 6 Nos. |
Layout and design
The layout plans indicate a series of residential blocks arranged around internal roads. The project includes a required common plot area of 1,696.17 square metres, while the applicant has proposed a larger area of 2,227.72 square metres. Internal roads will range from 6.0 metres to 7.5 metres in width to facilitate smooth traffic movement. Separate entry and exit gates are planned to manage vehicle flow.
Water, power and access
Water for the project will be managed through several conservation measures. During the construction phase, sewage will be disposed of via soak pits or septic systems. For the operational phase, the applicant proposes an 800 KLD (kilolitres per day) Activated Sludge Process (ASP) type Sewage Treatment Plant (STP). Treated sewage will be reused for gardening and flushing within the premises, with any excess discharged into the AMC drainage line.
To reduce fresh water demand, the project will use low-flush toilets, sensor-based fixtures, and drip irrigation for landscaping. Rainwater harvesting will be implemented through six percolation wells and an RCC collection tank for firefighting and gardening use.
Power will be supplemented by a 558 KW rooftop solar energy system, requiring approximately 5,580.56 square metres of terrace space. Diesel Generator (DG) sets with acoustic enclosures will be provided for emergency backup. The project also includes 70 electric vehicle (EV) charging stations with 7.5 KW fast chargers.
Environmental safeguards
The applicant has allocated a capital budget of ₹954.95 lakh for the Environmental Management Plan (EMP), with an annual recurring cost of ₹25.5 lakh. Key environmental measures include:
- Air Quality: Dust suppression through water sprinkling, 15-foot high boundary barricades during construction, and the use of RCC internal roads to minimize dust during operation.
- Waste Management: An automatic Organic Waste Converter (OWC) with a capacity of 2,500 kg per day will treat wet waste on-site. Separate bins will be provided for dry and wet waste segregation.
- Greenbelt: A thick plantation area of 1,273 square metres is planned, featuring 531 trees of native species to provide noise attenuation and ecological benefits.
- Noise Control: Use of anti-vibration pads for machinery and restricted construction hours (daytime only).
Slum Rehabilitation Project (AMC) Slum Policy, 2013 AHMEDABAD MUNICIPAL CORPORATION site plan and layout
2 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
1,175 applications in Ahmadabad since January 2022 are in the same category (Buildings & townships): 916 approved, 201 filed or under review, and 58 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 5.2 acres, this one is larger than 88% of them.
123 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Vadaj, Sabarmati, Ahmadabad, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Slum Rehabilitation Scheme — environmental approval granted, 50 m away
- Slum Rehabilitation Scheme — environmental approval granted, 50 m away
- Integrated Group Housing Facility Sector - 4/A — environmental approval granted, 150 m away
- Integrated Group Housing Facility Sector 5/A - 2 — environmental approval granted, 300 m away
- Integrated Group Housing Facility By AMC Under Mukhyamantri Gruh Yojana — environmental approval granted, 450 m away
- The Centrium II — environmental approval granted, 900 m away
- Proposed Slum Networking Project for Residential Affordable Housing with… — environmental approval granted, 1.1 km away
- Eternity — environmental approval granted, 1.5 km away
All 3 Shree Infracon projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.