Quick answers
What is this project?
Laying of Pipeline of Length 191 Km From Churwa to Bhabhar(Ips-1) Section of New Mundra Panipat Crude Oil Pipeline Project of Capacity 17.5 Mmtpa is an approved pipeline project in Bambhansar, Rapar, Kachchh, Gujarat. The site covers 1,14,271.4 acres.
Who is building it?
The applicant is Indian Oil Corporation Limited (IOCL).
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 9 Feb 2024), as of 27 Nov 2026.
Where is it?
In Bambhansar, Rapar, Kachchh, Gujarat.
How big is it?
It has a stated cost of ₹1,040 crore and a site of 1,14,271.4 acres.
When was it filed?
The application was filed on 2 Nov 2023.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 9 Feb 2024 |
| Application filed | 2 Nov 2023 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Pipelines |
| Applicant | Indian Oil Corporation Limited (IOCL) |
| Land area | 1,14,271.4 acres (46,244.1 ha) |
| Project cost | ₹1,040 crore |
| Village / locality | Bambhansar |
| Taluk / tehsil | Rapar |
| District | Kachchh |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-01091 |
In context
59 applications in Kachchh since January 2022 are in the same category (Pipelines): 21 approved, 25 filed or under review, and 13 withdrawn, lapsed or rejected. The approved ones took a median of 6 months from filing to approval. At 1,14,271.4 acres, this one is larger than 98% of them.
Where it is
Bambhansar, Rapar, Kachchh, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Kapdi Narendra Kanji 01.94.96 Ha. — under environmental review, 5.7 km away
- Shri Gohil Kanjee Bhikha — environmental approval granted, 5.8 km away
- Mining project by M/s KBG RMS Mines Private Limited — under environmental review, 5.9 km away
- Capacity Expansion of Jamnagar-Loni Pipeline (JLPL), GJ — more information requested, 6.2 km away
- Shri Dot Ramesh Vela. — under environmental review, 6.5 km away
- Shri Dot Ramesh Vela. — environmental approval granted, 6.5 km away
- Sadbhav Engineering Limited-3378 — more information requested, 6.8 km away
- Sadbhav Engineering Limited-3271 — more information requested, 7 km away
All 822 Indian Oil Corporation (IOCL) projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.