One of 2 filings for this project. The project's main page, with every filing and where each stands: Savgadh Granite Mine of M/S VISV Steels Co Pvt Ltd
Project details
| Status | Not approved |
|---|---|
| Status since | 3 Apr 2025 |
| Application filed | 23 Oct 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | V.I.S.V Steels company Private limited |
| Land area | 9.9 acres (4 ha) |
| Project cost | ₹1.2 crore |
| Village / locality | Savgadh |
| Taluk / tehsil | Idar |
| District | Sabar Kantha |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-02832 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 23 Oct 2024 (this page) | Not approved | 9.9 acres | ₹1.2 crore |
| New project filed 22 Oct 2024 | Environmental approval granted | 9.9 acres | ₹1.4 crore |
In context
226 applications in Sabar Kantha since January 2022 are in the same category (Mining): 124 approved, 37 filed or under review, and 65 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 9.9 acres, this one is larger than 87% of them.
No other mining lease on record is within 500 m of this site; 9 have applied within 5 km.
Where it is
Savgadh, Idar, Sabar Kantha, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Savgadh Granite Mine of M/S VISV Steels Co Pvt Ltd — environmental approval granted, 150 m away
- Savagdh Granite Mione of Chelaram mali (Transfer to M/S Pitambara Granite) — not approved, 800 m away
- Shri Hiteshkumar Umashankar Bhatt — lapsed, 900 m away
- Savgadh Granite Mine of shri Manojkumar Motilal Nandvala — environmental approval granted, 950 m away
- M/s Shree Rajendra Stone Pvt. Ltd., Re-appraisal of Environment Clearance… — environmental approval granted, 1.5 km away
- CConstruction of Ramp at Village - Mohanpura (Area 0.0722 Ha.) — more information requested, 1.7 km away
- Laloda Granite Mining Project, Survey No. 516 Paiki, Proposed by M/S. Manico… — not approved, 1.7 km away
- Laloda Granite Mine Survey No-516 P (Area-1.94.72Ha.) of M/S Greenshila Marble… — not approved, 1.8 km away
About this information