Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 3 Aug 2024 |
| Application filed | 29 Apr 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Ahmedabad Municipal Corporation |
| Use | Residential |
| Units | 598 |
| Towers | 6 |
| Floors (tallest) | 13 |
| Basements | 1 |
| Parking spaces | 486 |
| Land area | 3.5 acres (1.4 ha) |
| Built-up area | 69,065 m² (7,43,409 sq ft) |
| Plot area | 14,225 m² (1,53,116 sq ft) |
| Project cost | ₹106.8 crore |
| Village / locality | Chandkeda |
| Taluk / tehsil | Sabarmati |
| District | Ahmadabad |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-04328 |
What the filings say
What is planned
The Ahmedabad Municipal Corporation (AMC) has received environmental approval for a new Low Income Group (LIG) housing project in Chandkeda. The project is planned on a plot area of 14,225 square metres (1.42 hectares).
The layout plan specifies the construction of six residential blocks (Block 1 to 6) and a club house. Each residential block is designed with 13 floors above the ground level. The project will provide a total of 598 residential units.
Project Components
| Item | Detail |
|---|---|
| Total Residential Units | 598 |
| Number of Blocks | 6 Residential + 1 Club House |
| Maximum Floors | 13 Floors |
| Total Built-up Area | 69,084.54 sq.m. |
| F.S.I. Area | 42,675.00 sq.m. |
| Common Plot Area | 1,980.72 sq.m. |
| Green Space Area | 855.69 sq.m. |
Layout and design
The residential blocks are arranged around central common plots. The ground floor of the blocks is designated for hollow plinth parking. The site includes a dedicated club house building with a ground floor and first floor, featuring a hall, store, and toilets.
Infrastructure for the project includes a security cabin, an electrical substation, a Diesel Generator (DG) set area, and a Sewage Treatment Plant (STP). The internal road network is designed with 2.00-metre wide pathways with a 1:12 slope for pedestrian access. Fire safety design includes refuge areas on the 5th, 8th, and 12th floors of the residential blocks.
Water, power and access
During the construction phase, water will be supplied by the AMC. For the operational phase, the total wastewater generation is estimated at 323 kilolitres per day (KLD). The applicant proposes to recycle 161 KLD of this water, while the remaining 162 KLD will be drained into the AMC drainage line. A 350 KLD capacity STP using Moving Bed Biofilm Reactor (MBBR) technology is planned.
Power will be supplemented by a rooftop solar energy system with a capacity of 215.46 KW, requiring 1,294.72 square metres of terrace space. A DG set will be installed for emergency backup. Access to the site is provided via a 30.00-metre wide Town Planning Scheme (TPS) road.
Environmental safeguards
The Environment Management Plan (EMP) includes several mitigation measures:
- Air Quality: Regular sprinkling of water on haul roads, covering transportation vehicles with tarpaulin, and providing a minimum stack height of 3.5 metres above the roof for the DG set.
- Water Management: Four percolating wells are planned for rainwater harvesting and groundwater recharge. A dual plumbing system will be implemented to use recycled water.
- Noise Control: DG sets will be housed in acoustic enclosures. A green belt will be developed to act as a noise barrier.
- Solid Waste: An automatic Organic Waste Converter (OWC) with a capacity of 1,000 kg per day is proposed to handle biodegradable waste. Non-biodegradable waste will be segregated and sold to recyclers.
- Greenery: The applicant plans to plant 356 trees within the project premises.
Fire and Safety
The project will be equipped with a comprehensive fire hydrant system, including a 1,00,000-litre underground water tank and a 20,000-litre overhead tank. Fire safety installations include hose reels, fire extinguishers (DCP and CO2 types), fire lifts, and an automatic sprinkler system for the basement area. Photo-luminescent signage will be installed along all exit routes.
AMC LIG Housing Project site plan and layout
A drawing from the project's filings. Sign in free to see it.
🔒 Sign in free to see itIn context
1,175 applications in Ahmadabad since January 2022 are in the same category (Buildings & townships): 916 approved, 201 filed or under review, and 58 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 3.5 acres, this one is larger than 81% of them.
174 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Chandkeda, Sabarmati, Ahmadabad, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Residential and Commercial (Essential Shops) Project "ANAND ELEVATE" — environmental approval granted, 300 m away
- The Gold — environmental approval granted, 400 m away
- Jay Visat Atulyamm — initial checks, 900 m away
- Home Town-3 — environmental approval granted, 1000 m away
- Siddharth Gardenia — environmental approval granted, 1.1 km away
- Wertical Edge — under environmental review, 1.2 km away
- Sahajanand Hights — environmental approval granted, 1.3 km away
- Shree Kalash — environmental approval granted, 1.4 km away
More from Ahmedabad Municipal Corporation in Ahmadabad
- Environmental Clearance for proposed Ahmedabad City Square located Opposite… — initial checks
- Environmental Clearance for Development in Buffer Zone of Closed TSDF Facility… — under environmental review
- Slum Rehabilitation Scheme — environmental approval granted
- Environmental Clearance for Proposed Urban House (Public Institutional… — more information requested
- AMC Housing Project — lapsed
- Waste management project by M/s. Ahmedabad Municipal Corporation — environmental approval granted
All 11 Ahmedabad Municipal Corporation projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.