Quick answers
What is Kishanbhai Thagiyabhai Gamit?
Kishanbhai Thagiyabhai Gamit is a lapsed mining project in Limbi, Songadh, Tapi, Gujarat.
Who is building it?
The applicant is Gamit Kishanbhai Thagiya.
Has it been approved?
No. The application was lapsed on 30 Dec 2024, so it is no longer under consideration.
Where is it?
In Limbi, Songadh, Tapi, Gujarat.
How big is it?
It has a stated cost of ₹30 lakh.
When was it filed?
The application was filed on 24 Oct 2024.
Project details
| Status | Lapsed |
|---|---|
| Status since | 30 Dec 2024 |
| Application filed | 24 Oct 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Gamit Kishanbhai Thagiya |
| Project cost | ₹30 lakh |
| Village / locality | Limbi |
| Taluk / tehsil | Songadh |
| District | Tapi |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-04766 |
In context
100 applications in Tapi since January 2022 are in the same category (Mining): 9 approved, 14 filed or under review, and 77 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval.
No other mining lease on record is within 500 m of this site; 7 have applied within 5 km.
Where it is
Limbi, Songadh, Tapi, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Shri Dahyabhai Somabhai Ode, Vadibhesrot Ordinary Sand Mining Project — more information requested, 1.2 km away
- Shri Shivji Valji Pindoriya Re-appraisal Area-1.00 Survey no.–368 P (Pvt.… — lapsed, 1.4 km away
- Shri Ashishbhai R. Shah. Re-appraisal Area-2.00.00 Survey no.- 223,260,400 ni… — lapsed, 1.4 km away
- Widening and Strengthening of Songadh Ukai Sherulla Road (KM 2/800 to 18/500)… — more information requested, 2.1 km away
- Laying of 66kV 630 sq mm (3+1) XLPE Underground cable for 66KV Ukai - Satkashi… — forest land use approved, 3.2 km away
- Shri Nareshbhai Dahyabhai Ode, Borisavar Ordinary Sand Mining Project — more information requested, 3.4 km away
- Shri Jusabbhai Ismailbhai Malek Re-appraisal Area- 1.35.00 Survey no.- Opp. S.… — lapsed, 3.7 km away
- Laying of 66kV 630 sq mm (3+1) XLPE Underground cable for 66KV Ukai - Bhimpura… — forest land use approved, 4.2 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.