One of 2 filings for this project. The project's main page, with every filing and where each stands: Industrial project by M/s. Oryn Healthcare LLP
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 12 Jul 2024 |
| Application filed | 13 Apr 2024 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Oryn Healthcare LLP |
| Land area | 2.2 acres (0.9 ha) |
| Project cost | ₹3 crore |
| Village / locality | Vadpura |
| Taluk / tehsil | Kadi |
| District | Mahesana |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-06576 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 12 Apr 2025 | Environmental approval granted | 2.2 acres | ₹3 crore |
| Early planning filed 13 Apr 2024 (this page) | Cleared for impact study | 2.2 acres | ₹3 crore |
In context
113 applications in Mahesana since January 2022 are in the same category (Industry): 80 approved, 25 filed or under review, and 8 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 2.2 acres, this one is smaller than 53% of them.
6 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Vadpura, Kadi, Mahesana, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Industrial project by M/s. Oryn Healthcare LLP — environmental approval granted, 0 m away
- Industrial project by M/s. ANBUVA PHARMA PRIVATE LIMITED — environmental approval granted, 400 m away
- Industrial project by Heavy Metal and Tubes (India) Pvt. Ltd. — cleared for impact study, 600 m away
- Approach road to connect Kanaiya Exports Pvt Ltd, village Ganeshpura, District… — forest land use approved, 2 km away
- PROPOSED PROJECT FOR SYNTHETIC ORGANIC CHEMICALS [DYE INTERMEDIATES]… — cleared for impact study, 2.3 km away
- Environment Clearance for Proposed Green Field Project for Manufacturing of… — cleared for impact study, 2.5 km away
- Proposed new project of Manufacturing of Synthetic Organic Chemicals(API,… — cleared for impact study, 3.2 km away
- Industrial project by M/s. Dhyaavee TMT Bars Private Limited — environmental approval granted, 5.1 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.