Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 9 Jul 2024 |
| Application filed | 2 Apr 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Venus Projects LLP |
| Use | Mixed use |
| Units | 293 |
| Towers | 2 |
| Floors (tallest) | 14 |
| Basements | 2 |
| Parking spaces | 499 |
| Land area | 2.2 acres (0.9 ha) |
| Built-up area | 58,534 m² (6,30,054 sq ft) |
| Plot area | 8,863 m² (95,400 sq ft) |
| Project cost | ₹85.5 crore |
| Village / locality | Makarba |
| Taluk / tehsil | Sabarmati |
| District | Ahmadabad |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-06754 |
What the filings say
What is planned
Venus Projects LLP proposes a mixed-use development consisting of residential and commercial spaces. The project involves the construction of six blocks, identified as Blocks A to F, on an amalgamated plot. According to the applicant's project report, the residential component includes 286 units, while the commercial section will feature 7 shops. The buildings are designed with a maximum height of 14 floors above ground level, supported by two basement levels for parking.
Layout and design
The project is planned with a total built-up area of 33,754.93 sq. m. and a total Floor Space Index (FSI) area of 31,884.62 sq. m. The site includes a hollow plinth for parking and two basement levels, each covering 6,404.47 sq. m. Open spaces are provided through two common plots totaling 1,113.42 sq. m. The layout includes a 5.18m wide pathway and a 6.0m wide approach road.
| Item | Detail |
|---|---|
| Residential units | 286 |
| Commercial shops | 7 |
| Tallest building | 14 floors |
| Total water requirement | 270.54 KLD |
| STP capacity | 250 KLD |
| Greenbelt area | 1,113.42 sq. m. |
| Tree plantation | 222 trees |
| Environmental budget | ₹97.5 lakh |
Land and surroundings
The site is located at Final Plot No. 51 and 57 in Makarba, Ahmedabad, opposite the Makarba Police Headquarters. The geotechnical investigation report describes the surface as uneven ground. Subsurface testing revealed layers of firm black clayey silt up to 1.5m, followed by stiff brown clayey silt and medium brown silty sand with kankar. The groundwater table was encountered at a depth of 6.7m, with a design water table suggested at 5m.
Water, power and access
The total water requirement for the operation phase is estimated at 270.54 kilolitres per day (KLD). This includes a fresh water requirement of 182.96 KLD and a recycled water requirement of 87.58 KLD for flushing and gardening. During construction, the water demand is 17.5 KLD. Power will be supplied from a nearby 132 KV electric grid line. The project site is accessible via 18m and 40m wide Town Planning Scheme roads.
Environmental safeguards
The applicant proposes to install a Sewage Treatment Plant (STP) with a capacity of 250 KLD. For storm water management, three percolation wells will be developed to recharge groundwater, with an estimated annual recharge volume of 3,800 cubic metres. The greenbelt plan covers 1,113.42 sq. m. and involves planting 222 trees in two phases. A capital budget of ₹97.5 lakh is allocated for environmental management, including ₹30 lakh for the STP and ₹21 lakh for air pollution control measures.
Safety features
Fire safety installations will include a 2,50,000-litre underground static water storage tank and 20,000-litre terrace tanks for each block. The buildings will be equipped with wet risers, automatic sprinklers in the basement and commercial areas, and manually operated electric fire alarm systems.
Palm Jumeirah site plan and layout
4 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
1,175 applications in Ahmadabad since January 2022 are in the same category (Buildings & townships): 916 approved, 201 filed or under review, and 58 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 2.2 acres, this one is larger than 70% of them.
163 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Makarba, Sabarmati, Ahmadabad, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Sumaya — environmental approval granted, 250 m away
- Seventh Heaven 2 — environmental approval granted, 300 m away
- Proposed Residential and Commercial Project - "HUSAINI BAGH" — environmental approval granted, 400 m away
- Expansion of Blue Ocean (Residential and Commercial High-Rise Building… — environmental approval granted, 650 m away
- Blue Ocean (Residential & Commercial building construction project) — environmental approval granted, 650 m away
- "HR Eliseo-IV" - Residential Apartment with Shops to be developed by "HR… — environmental approval granted, 700 m away
- Al Hoor — environmental approval granted, 900 m away
- Al Noor — environmental approval granted, 950 m away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.