Quick answers
What is "pramukh Pinnacle"?
"pramukh Pinnacle" is an approved residential project in Por, Gandhinagar, Gujarat. It plans 240 units in 4 towers of up to 14 floors on 1.2 acres.
Who is building it?
The applicant is Patel Hiteshkumar Bababhai.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 3 Apr 2025), as of 27 Nov 2026.
Where is it?
In Por, Gandhinagar, Gujarat.
How big is it?
It has a stated cost of ₹54.8 crore and a site of 1.2 acres.
When was it filed?
The application was filed on 8 Nov 2024.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 3 Apr 2025 |
| Application filed | 8 Nov 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Patel Hiteshkumar Bababhai |
| Use | Residential |
| Units | 240 |
| Towers | 4 |
| Floors (tallest) | 14 |
| Basements | 2 |
| Height | 45 m |
| Parking spaces | 303 |
| Land area | 1.2 acres (0.5 ha) |
| Built-up area | 32,132 m² (3,45,866 sq ft) |
| Plot area | 4,937 m² (53,141 sq ft) |
| Project cost | ₹54.8 crore |
| Village / locality | Por |
| Taluk / tehsil | Gandhinagar |
| District | Gandhinagar |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-06833 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 8 Nov 2024 (this page) | Environmental approval granted | 1.2 acres | ₹54.8 crore |
| New project filed 22 Oct 2024 | Withdrawn | 1.2 acres | ₹54.8 crore |
What the filings say
What is planned
Patel Hiteshkumar Bababhai is proposing a residential and commercial building project named "Pramukh Pinnacle" in Por village, Gandhinagar. According to the applicant's project report, the development will consist of four blocks (A, B, C, and D) with a total built-up area of 32,132 square metres on a plot of 0.49 hectares (1.22 acres).
The project includes 24 commercial units and 216 residential units. The building configuration features two basement levels for parking, a ground floor for commercial use, and 14 upper floors.
| Item | Detail |
|---|---|
| Total Built-up Area | 32,132 sq. m. |
| Plot Area | 4,937 sq. m. |
| Residential Units | 216 |
| Commercial Units | 24 |
| Tallest Building | Ground + 14 floors |
| Basement Levels | 2 |
| Common Plot Area | 524.53 sq. m. |
Layout and design
The layout plan indicates that Block A and Block B are situated at the front of the plot, while Block C and Block D are located towards the rear. The ground floor is dedicated to commercial shops, with 24 units planned across the blocks. The upper floors (1st to 14th) are designed for residential use, with four units per floor in each block.
The basements are designated for parking, with the second basement specifically noted for four-wheeler parking and the first basement accommodating both two-wheeler and four-wheeler parking for residents. The site includes internal roads of 6.0 metres width and is bordered by 18.0-metre wide Town Planning (TP) roads on multiple sides.
Water, power and access
During the construction phase, water will be sourced from local tanker suppliers. For the operation phase, the applicant intends to meet the water requirement through the Gandhinagar Municipal Corporation (GMC) supply. A water metering system will be installed to track usage.
Power requirements will be supported by the state electricity grid, with Diesel Generator (DG) sets provided for emergency backup. These sets will be housed in acoustic enclosures to mitigate noise. Access to the site is provided via the surrounding 18.0-metre wide TP roads.
Environmental safeguards
The Environmental Management Plan (EMP) outlines several mitigation measures:
- Water and Wastewater: Domestic sewage during construction will be disposed of through a septic tank and soak pit system. During operation, sewage will be discharged into the GMC drainage line. Rainwater harvesting structures, including roof catchments and storage tanks, will be installed.
- Waste Management: Construction debris will be used for levelling or road construction. During the operation phase, municipal solid waste will be segregated into dry and wet waste. Organic waste will be composted on-site for use in greenbelt development.
- Air and Noise: Tarpaulin covers and water sprinkling will be used to control dust during construction. Peripheral barricading will be erected to prevent dust from spreading outside the premises.
- Greenbelt: The applicant plans to develop a greenbelt consisting of tree-covered and lawn areas within the project premises.
- Energy Conservation: The project will use LED lighting for common areas, solar water heating systems, and energy-efficient motors and pumps. Solar lights will be installed in open sunlit areas.
Pramukh Pinnacle site plan and layout
4 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
472 applications in Gandhinagar since January 2022 are in the same category (Buildings & townships): 365 approved, 79 filed or under review, and 28 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 1.2 acres, this one is smaller than 64% of them.
213 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Por, Gandhinagar, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Pramukh Pinnacle — withdrawn, 0 m away
- Proposed Residential and Commercial Project - "Shree Sharanam Setu" — environmental approval granted, 50 m away
- Pramukh Pentagon — environmental approval granted, 150 m away
- Proposed Residential & Commercial (Essential Shop) Project - "The Palm Unity" — environmental approval granted, 200 m away
- Proposed Residential & Commercial (Essential Shop) Project - "The Palm Unity" — lapsed, 200 m away
- "Residential Cum Commercial Project – Sargam Sarita 2.0" by M/s. Sargam… — environmental approval granted, 300 m away
- "RIVANTA 2" (New name: RIVANTA AUROVILE) — lapsed, 350 m away
- The Beverly Heights — environmental approval granted, 400 m away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.