Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 2 Aug 2025 |
| Application filed | 24 Mar 2025 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Harvin Developer LLP |
| Use | Residential |
| Units | 38 |
| Towers | 1 |
| Floors (tallest) | 21 |
| Basements | 1 |
| Height | 75 m |
| Parking spaces | 127 |
| Land area | 1 acres (0.4 ha) |
| Built-up area | 26,988 m² (2,90,496 sq ft) |
| Plot area | 4,134 m² (44,498 sq ft) |
| Project cost | ₹29.6 crore |
| Village / locality | Mota Mava |
| Taluk / tehsil | Rajkot |
| District | Rajkot |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-07193 |
What the filings say
What is planned
Harvin Developer LLP proposes to develop Harmony Pride, a high-rise residential project in Mota Mava, Rajkot. The project report describes a single building with a maximum height of 70.00 metres, consisting of a basement, ground floor, and 21 upper floors.
The development is planned to house 38 dwelling units in total. The floor-wise distribution of units is as follows:
- Ground Floor: 2 units
- 1st to 19th Floors: 2 units per floor
- 20th and 21st Floors: 1 unit per floor
Key Figures
| Item | Detail |
|---|---|
| Total Plot Area | 4,134.00 sq. mt. |
| Total Built-up Area | 16,515.14 sq. mt. |
| Height of Building | 70.00 metres |
| Total Dwelling Units | 38 |
| Common Plot Area | 413.49 sq. mt. |
| Green Area | 415.0 sq. mt. |
| Total Parking Provided | 4,404.67 sq. mt. |
| Solar Power Capacity | 173.00 K.W. |
Layout and design
The building is designed as a frame structure. The ground floor and first floor are dedicated to parking and services, while residential units begin from the ground floor up to the 21st floor. The layout includes a common plot of 413.49 square metres (approximately 10% of the plot area).
Vertical circulation is managed by four lifts, including one dedicated fire lift. The building design incorporates architectural features for energy conservation, such as natural ventilation for public areas and building orientation to maximize daylight.
Water, power and access
The project site is accessed via an 18.00-metre wide Town Planning (T.P.) road. A 4.50-metre wide internal access path is also provided.
Water Supply: The applicant proposes to minimize fresh water consumption through water-efficient plumbing fixtures and leak detection. Rainwater harvesting is planned with two percolation wells to recharge groundwater. A sewage treatment plant will be installed to treat wastewater, which will then be reused for landscaping, flushing, and cooling for Diesel Generator (DG) sets.
Power: The connected load requirements will be partially met by solar power, with a provided capacity of 173.00 K.W. DG sets will be used for backup power, housed in acoustic enclosures to mitigate noise.
Parking: Total parking area provided is 4,404.67 square metres, exceeding the required 3,303.03 square metres. This includes 1,717.10 square metres of mechanical parking in the basement, 1,500.36 square metres on the ground floor, and 1,187.21 square metres on the first floor. A dedicated visitor parking area of 340.63 square metres is also included.
Environmental safeguards
The Environment Management Plan (EMP) outlines several mitigation measures:
- Air Quality: Dust control during construction using water sprinking and covering of transport loads. Stack heights for DG sets will be maintained for proper pollutant dispersion.
- Noise Control: Noisy construction activities will be restricted to daytime. Acoustic enclosures for DG sets will ensure noise levels do not exceed 75 dB(A) at one metre.
- Waste Management: Solid waste will be segregated at source. Organic waste will be treated using an organic waste converter or vermicomposting. Recyclable waste will be sold to authorized vendors. The project requires five solid waste bins of 80-litre capacity.
- Greenbelt: A total green area of 415.0 square metres (10.03% of the net plot area) is planned. The applicant intends to plant 104 trees using native and fast-growing species.
- Fire Safety: The plan includes a 1,00,800-litre underground water tank for fire fighting and a 20,000-litre terrace tank. Sprinkler systems, fire hydrants, and fire extinguishers will be installed on every floor.
Harvin Developer Residential Project Harmony Pride site plan and layout
4 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
134 applications in Rajkot since January 2022 are in the same category (Buildings & townships): 109 approved, 17 filed or under review, and 8 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 1 acre, this one is smaller than 93% of them.
95 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Mota Mava, Rajkot, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Residential Project by Smt. Vijyaben M Vaghani & Others — environmental approval granted, 150 m away
- Proposed Residential Project by Shri Kishorbhai Ghelabhai Pokar & Others — environmental approval granted, 350 m away
- Residential Building Project by Aquablue Enterprise Owners Association — environmental approval granted, 550 m away
- Residential Building Project Sky Line Proposed by Cosmos Habitate LLP — environmental approval granted, 600 m away
- Proposed Residential building construction Project Shyamal Shrushti by Shyamal… — environmental approval granted, 700 m away
- Proposed Residential building construction Project Shyamal Shrushti by Shyamal… — environmental approval granted, 700 m away
- Proposed Residential Project by Acute Buildcon LLP — environmental approval granted, 800 m away
- Proposed Residential Cum Commercial Building Construction Project Rk… — initial checks, 900 m away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.