What is Jetty and Desalination Plant?
Jetty and Desalination Plant is an approved port and coastal project in Akri Moti, Abdasa, Kachchh, Gujarat. The site covers 139.2 acres.
Who is building it?
The applicant is Vadraj Cement Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 22 Jul 2026), as of 27 Nov 2026.
Where is it?
In Akri Moti, Abdasa, Kachchh, Gujarat.
How big is it?
It has a stated cost of ₹123.8 crore and a site of 139.2 acres.
When was it filed?
The application was filed on 10 Dec 2025.
Project details
| Official title | Construction of Jetty and Desalination Plant at Village Thumdi Akrimoti, District Kutch, Gujarat |
|---|---|
| Status | Environmental approval granted |
| Status since | 22 Jul 2026 |
| Application filed | 10 Dec 2025 |
| Approval sought | Environmental approval |
| Application type | Ownership transfer |
| Sector | Ports & coast |
| Applicant | Vadraj Cement Limited |
| Land area | 139.2 acres (56.4 ha) |
| Project cost | ₹123.8 crore |
| Village / locality | Akri Moti |
| Taluk / tehsil | Abdasa |
| District | Kachchh |
| State | Gujarat |
| Location from | Site area on record |
| Our reference | WID-GJ-07395 |
In context
36 applications in Kachchh since January 2022 are in the same category (Ports & coast): 13 approved, 16 filed or under review, and 7 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 139.2 acres, this one is smaller than 63% of them.
6 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Akri Moti, Abdasa, Kachchh, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Diversion of 60.98 Ha of Forest Land for Construction of Jetty and Other… — under forest review, 2.3 km away
- Expansion of Sanghi Port at Kharo Creek, Kachchh District, Gujarat. — returned to applicant, 2.8 km away
- Expansion of Sanghi Port at Kharo Creek, Kachchh district, Gujarat. — more information requested, 2.8 km away
- Transfer of Environmental Clearance and its amendment granted to Sanghi… — environmental approval granted, 2.8 km away
- Application for Transfer of 88.123 Ha Forest Land Permission for Construction… — under forest review, 2.8 km away
- Transfer of Environmental Clearance and its amendment granted to Sanghi… — environmental approval granted, 3.1 km away
- Setting up of Cement Plant (3.3 MMTA) — environmental approval granted, 6 km away
- Setting up of Cement Plant (3.3 MMTA) — environmental approval granted, 6 km away
More from Vadraj Cement Limited in Kachchh
- Setting up of Cement Plant (3.3 MMTA) — environmental approval granted
- Setting up of Cement Plant (3.3 MMTA) — environmental approval granted
- Name change in Environmental Clearance of Naniber Limestone Mining Project of… — lapsed
- Setting up of Cement Plant (3.3 MMTA) — returned to applicant
5 Vadraj Cement projects in Kachchh
All 8 Vadraj Cement projects across India