What is M/s Urja Stone Quarry. C/o Shri Tejas Amarsingh Choudhary?
M/s Urja Stone Quarry. C/o Shri Tejas Amarsingh Choudhary is a proposed mining project in Bamnamal, Vyara, Tapi, Gujarat. The site covers 2.1 acres.
Who is building it?
The applicant is Chaudhary Tejas Amarsinh.
Has it been approved?
Not yet. The application is still under review: its status is “Returned to applicant”, as of 27 Nov 2026.
Where is it?
In Bamnamal, Vyara, Tapi, Gujarat.
How big is it?
It has a stated cost of ₹3 crore and a site of 2.1 acres.
When was it filed?
The application was filed on 12 Aug 2025.
Project details
| Status | Returned to applicant |
|---|---|
| Status since | 5 Jan 2026 |
| Application filed | 12 Aug 2025 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Chaudhary Tejas Amarsinh |
| Land area | 2.1 acres (0.8 ha) |
| Project cost | ₹3 crore |
| Village / locality | Bamnamal |
| Taluk / tehsil | Vyara |
| District | Tapi |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-07421 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 12 Aug 2025 (this page) | Returned to applicant | 2.1 acres | ₹3 crore |
| Early planning filed 26 Apr 2025 | Lapsed | 2.1 acres | ₹3.7 crore |
In context
100 applications in Tapi since January 2022 are in the same category (Mining): 9 approved, 14 filed or under review, and 77 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 2.1 acres, this one is smaller than 87% of them.
5 other mining leases have applied within 500 m of this site; together with this one they cover 28 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 6 mining leases have applied within 5 km.
Where it is
Bamnamal, Vyara, Tapi, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- M/s Urja Stone Quarry, C/o Shri Tejas Amarsingh Choudhary — lapsed, 0 m away
- M/s Urja Stone Quarry, C/o Shri Tejas Amarsingh Chaudhary Re-appraisal Area-… — not approved, 100 m away
- M/s Prabhat stone Quarry, Re-appraisal Area-1.82.16 Survey no. – 37 Paiki,… — not approved, 150 m away
- M/s Prabhat Stone Quarry (1.82.16) — returned to applicant, 150 m away
- Shri Rajnikant Gordhanbhai Chaniyara — returned to applicant, 250 m away
- Shri Rajnikant Gordhanbhai Chaniyara Re-appraisal Area-3.00.53Survey no. - 66… — not approved, 250 m away
- FCA Proposal of diversion of Forest Area 0.0285 Ha to set up Solar Park — forest land use approved, 1.8 km away
- KHANPUR ORDINARY SAND QUARRY LEASE (Submitted Under Rule 38 of GMMCR 2017)… — not approved, 4.2 km away
More from Chaudhary Tejas Amarsinh in Tapi
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.