Quick answers
What is Shri Ankit Rameshchandra Thacker?
Shri Ankit Rameshchandra Thacker is a proposed mining project in Dagala, Bhuj, Kachchh, Gujarat. The site covers 6.4 acres.
Who is building it?
The applicant is Ankit Ramesh Thacker.
Has it been approved?
Not yet. The application is still under review: its status is “Returned to applicant”, as of 27 Nov 2026.
Where is it?
In Dagala, Bhuj, Kachchh, Gujarat.
How big is it?
It has a stated cost of ₹5.5 crore and a site of 6.4 acres.
When was it filed?
The application was filed on 13 Dec 2025.
Project details
| Status | Returned to applicant |
|---|---|
| Status since | 18 Feb 2026 |
| Application filed | 13 Dec 2025 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Mining |
| Applicant | Ankit Ramesh Thacker |
| Land area | 6.4 acres (2.6 ha) |
| Project cost | ₹5.5 crore |
| Village / locality | Dagala |
| Taluk / tehsil | Bhuj |
| District | Kachchh |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-09048 |
In context
1,132 applications in Kachchh since January 2022 are in the same category (Mining): 683 approved, 276 filed or under review, and 173 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 6.4 acres, this one is larger than 56% of them.
1 other mining lease has applied within 500 m of this site; together with this one they cover 16.6 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 75 mining leases have applied within 5 km.
Where it is
Dagala, Bhuj, Kachchh, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Ankit Rameshchandra Thacker — under environmental review, 0 m away
- Shri Thakkar Hiren — environmental approval granted, 150 m away
- Shri Thakkar Hiren — cleared for impact study, 150 m away
- Shri Varchand Lakhman Rupa — environmental approval granted, 700 m away
- Shri Varchand Lakhman Rupa — cleared for impact study, 700 m away
- Shri Daya Gopal Varchand — environmental approval granted, 750 m away
- Shri Daya Gopal Varchand — cleared for impact study, 750 m away
- Shri Varchand Bhagu Dana — initial checks, 850 m away
More from Ankit Ramesh Thacker in Kachchh
- Ankit Rameshchandra Thacker — under environmental review
- Ankit Rameshchandra Thacker — under environmental review
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.