Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 16 Jul 2025 |
| Application filed | 31 Jan 2025 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | aSHOK HARILAL TANNA |
| Use | Mixed use |
| Units | 235 |
| Towers | 1 |
| Floors (tallest) | 13 |
| Basements | 2 |
| Height | 45 m |
| Parking spaces | 485 |
| Land area | 1.7 acres (0.7 ha) |
| Built-up area | 36,433 m² (3,92,161 sq ft) |
| Plot area | 6,725 m² (72,387 sq ft) |
| Project cost | ₹49.8 crore |
| Village / locality | Vadsar |
| Taluk / tehsil | Vadodara Rural |
| District | Vadodara |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-09565 |
What the filings say
What is planned
The applicant, Ashok Harilal Tanna, proposes the construction of a residential structure named "Atrius" in Vadsar, Vadodara. According to the project reports, the development will consist of a single building with a ground floor and 13 upper floors (G+13), supported by a double basement.
The project is designed primarily for residential use, with a total proposed floor space area of 24,192.52 square metres. The building height is planned to be 44.55 metres from ground level. The layout includes common sanitary provisions for commercial users, suggesting some commercial components within the development.
| Item | Detail |
|---|---|
| Total Plot Area | 6,725.00 sq. m. |
| Total Built-up Area (Ground Floor) | 2,939.85 sq. m. |
| Total Floor Space Area | 24,192.52 sq. m. |
| Building Height | 44.55 m |
| Tallest Structure | G+13 floors |
| Basement | Double basement |
| STP Capacity | 125 KLD |
Layout and design
The site plan indicates the building will be situated on a plot of 0.67 hectares (1.66 acres). The layout features several open parking areas:
- Open Parking 1: 345.52 sq. m.
- Open Parking 2: 672.50 sq. m.
- Open Parking 3: 307.64 sq. m.
- Open Parking 4: 754.18 sq. m.
A common plot of 672.50 square metres (10% of the plot area) is reserved. The design incorporates three lifts, each with a capacity for 24 passengers. For fire safety, the building will include a refuge area, fire extinguishers, a wet riser system, and automatic sprinklers, particularly in the basement parking areas. Water storage for fire fighting includes a 2,00,000-litre underground tank and two 20,000-litre terrace tanks.
Land and surroundings
The project site is located at Survey No. 59 and 58/A in Vadsar, within the Vadodara Rural sub-district. Geotechnical investigations involved drilling a borehole to a depth of 20 metres, revealing a soil profile of brownish medium dense silty soil, followed by yellowish medium dense fine-grained silty sand with kankars, and yellowish stiff to hard clayey soil. The groundwater table was encountered at a depth of 10.50 metres during the investigation in November 2024.
Water, power and access
The site is accessible via a 40-metre wide road and a 12-metre Town Planning (TP) road. During the operation phase, the total water requirement is estimated at 123.02 kilolitres per day (KLD). This includes 112.50 KLD for domestic use by an estimated 2,500 occupants, 7.5 KLD for visitors, and 3.02 KLD for horticulture.
Fresh water requirement is projected at 65 KLD, while 58.02 KLD of treated wastewater will be reused for flushing and gardening. The applicant plans to install a Sewage Treatment Plant (STP) with a capacity of 125 KLD. Power for the project will be supplemented by solar energy, with a required solar energy generation of 754.40 KW.
Environmental safeguards
The Environmental Management Plan (EMP) allocates a capital budget of ‡96.5 lakh for protection measures. Key safeguards include:
- Water Management: Rainwater will be collected through piped drains and directed to two percolation wells for groundwater recharge. An estimated 3,500 cubic metres will be recharged annually.
- Waste Management: Solid waste will be segregated into organic and inorganic components. Bio-degradable waste will be converted into compost, while recyclable inorganic waste will be sold.
- Greenbelt: A greenbelt is planned around the site perimeter and internal roads. This will be developed in two phases, initially planting evergreen trees at 3-metre intervals, followed by a second row of trees with larger canopies after 18 months.
- Air and Noise: Dust suppression through water sprinkling and the use of ear mufflers for workers are planned for the construction phase. The building design includes energy-efficient lighting and ventilation.
Atrius site plan and layout
4 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
179 applications in Vadodara since January 2022 are in the same category (Buildings & townships): 123 approved, 36 filed or under review, and 20 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 1.7 acres, this one is smaller than 61% of them.
59 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Vadsar, Vadodara Rural, Vadodara, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Sky Addresses — environmental approval granted, 300 m away
- Ria Grand Villa - 2 — environmental approval granted, 500 m away
- Ria Grand Villa- 2 — lapsed, 500 m away
- SWC Skylight — environmental approval granted, 550 m away
- Vande Mataram — environmental approval granted, 900 m away
- Shivanta Krushnam — environmental approval granted, 900 m away
- Engeering Inductries — withdrawn, 950 m away
- Survi Privilon — environmental approval granted, 1.1 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.