What is Developing? Open the mapMap

Environmental approval grantedBuildings & townships · Gandhinagar, Gujarat

Saral Gold

Saral Gold is an approved residential project in Bhat, Gandhinagar, Gujarat. The site covers 4.3 acres. Its stated project cost is ₹158.8 crore. As of 27 Nov 2026, its status is “Environmental approval granted” (since 27 Oct 2026).

See it on the live map All projects in Gandhinagar

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is Saral Gold?

Saral Gold is an approved residential project in Bhat, Gandhinagar, Gujarat. The site covers 4.3 acres.

Who is building it?

The applicant is Saral Developers.

Has it been approved?

Yes. Its status is “Environmental approval granted” (since 27 Oct 2026), as of 27 Nov 2026.

Where is it?

In Bhat, Gandhinagar, Gujarat.

How big is it?

It has a stated cost of ₹158.8 crore and a site of 4.3 acres.

When was it filed?

The application was filed on 25 May 2026.

Project details

StatusEnvironmental approval granted
Status since27 Oct 2026
Application filed25 May 2026
Approval soughtEnvironmental approval
Application typeAmendment
SectorBuildings & townships
ApplicantSaral Developers
UseResidential
Land area4.3 acres (1.7 ha)
Project cost₹158.8 crore
Village / localityBhat
Taluk / tehsilGandhinagar
DistrictGandhinagar
StateGujarat
Location fromSite boundary on record
Our referenceWID-GJ-09812

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
Amendment filed 25 May 2026 (this page)Environmental approval granted4.3 acres₹158.8 crore
New project filed 13 Aug 2024Environmental approval granted4.3 acres₹158.8 crore

What the filings say

What is planned

Saral Developers (also referred to as Jethwani Builders) proposes to construct a residential building project named Saral Gold in Bhat, Gandhinagar. The applicant's project report states the development will consist of nine residential blocks across a net plot area of 1.72 hectares (4.25 acres). The total built-up area is planned at 1,17,398.23 square metres.

The project comprises two basement levels, a ground floor (hollow plinth), and 12 upper floors. A total of 432 residential units are planned across the nine blocks (Blocks A to I). The ground floor and hollow plinth areas are primarily designated for parking and common amenities.

ItemDetail
Total Units432 residential flats
Number of Blocks9 (A, B, C, D, E, F, G, H, I)
Building HeightBasement 1 & 2 + GF + 12 Floors
Total Built-up Area1,17,398.23 square metres
Proposed FSI Area68,596.12 square metres
Total Parking Area28,253.75 square metres
Power Requirement3,500 KW (Torrent Power Ltd)
Solar Power Generation339 KW

Layout and design

The site layout includes four common plots totaling 1,751.80 square metres. Block A is a standalone structure, while other blocks are arranged in clusters. The design incorporates a 90-metre wide ring road and 12-metre wide service roads for access. Internal roads will be at least 6 metres wide to ensure smooth vehicular movement.

Common amenities include a society community amenity area, a club, and landscaped open spaces. The project features two basement levels dedicated to parking, with additional parking provided in the hollow plinth. The total parking capacity is planned for 902 cars, with 20% of the spaces equipped with electric vehicle (EV) charging facilities.

Water, power and access

During the construction phase, water requirements are estimated at 10.25 kilolitres per day (KLD), to be met via tankers. For the operation phase, the total water requirement is projected at 296 KLD. Of this, 178 KLD will be fresh water supplied by the Gandhinagar Urban Development Authority (GUDA), and 118 KLD will be recycled treated sewage for flushing and gardening.

Power will be sourced from Torrent Power Ltd. A 125 KVA diesel generator set is proposed for emergency backup. The applicant plans to install rooftop solar panels covering 50% of the terrace area (approximately 3,393 square metres) to generate 339 KW of power.

Environmental safeguards

The applicant proposes an onsite Sewage Treatment Plant (STP) with a capacity of 275 KLD. Treated sewage will be reused within the premises, with any surplus discharged into the GUDA drainage line. For solid waste, an Organic Waste Composter (OWC) with a capacity of 750 kg/day will be installed to treat wet waste. Inorganic waste will be sold to authorized recyclers.

To manage rainwater, five percolation wells are planned for groundwater recharging. The greenbelt will cover 1,030 square metres, including 864 square metres of tree-covered area with 432 trees. Dust mitigation measures during construction include 15-foot high barricading, water sprinkling, and covering construction materials with tarpaulin. The buildings are designed to be earthquake-resistant, adhering to Seismic Zone III standards.

Saral Gold site plan and layout

4 drawings from the project's filings. Sign in free to see them.

Saral Gold: Site layout: residential blocks, common plots, and internal road network (preview)🔒 Sign in free to see it
Site layout: residential blocks, common plots, and internal road network
Saral Gold: Building section: basement levels, hollow plinth, and 12 residential floors (preview)🔒 Sign in free to see it
Building section: basement levels, hollow plinth, and 12 residential floors
Saral Gold: Floor plans: typical unit layouts for residential blocks (preview)🔒 Sign in free to see it
Floor plans: typical unit layouts for residential blocks
Saral Gold: Master plan: parking layout, STP location, and utility zones (preview)🔒 Sign in free to see it
Master plan: parking layout, STP location, and utility zones

In context

472 applications in Gandhinagar since January 2022 are in the same category (Buildings & townships): 365 approved, 79 filed or under review, and 28 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 4.3 acres, this one is larger than 94% of them.

87 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Bhat, Gandhinagar, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Saral Developers in Gandhinagar

3 Saral Developers projects in Gandhinagar
All 4 Saral Developers projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.