Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 12 Jun 2026 |
| Application filed | 2 Mar 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Shiv Infrastructure |
| Use | Residential |
| Units | 200 |
| Towers | 2 |
| Floors (tallest) | 10 |
| Basements | 2 |
| Parking spaces | 272 |
| Land area | 3,800 m² |
| Built-up area | 25,447 m² (2,73,909 sq ft) |
| Plot area | 3,758 m² (40,451 sq ft) |
| Project cost | ₹58.3 crore |
| Village / locality | Tragad |
| Taluk / tehsil | Sabarmati |
| District | Ahmadabad |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-10382 |
What the filings say
What is planned
Shiv Infrastructure proposes the construction of a new residential and commercial project named "The Saffron" in Tragad, Ahmedabad. The applicant's project report describes a development consisting of three blocks (Block A, B, and C) on a plot area of 3,758.00 square metres.
The project is designed as a Residential Affordable Housing (RAH) project. It will feature 200 residential units and commercial shops. The total built-up area is planned at 25,447.47 square metres, with a total FSI (Floor Space Index) area of 12,131.56 square metres.
Key Figures
| Item | Detail |
|---|---|
| Total Plot Area | 3,758.00 square metres |
| Total Built-up Area | 25,447.47 square metres |
| Total FSI Area | 12,131.56 square metres |
| Total Residential Units | 200 |
| Total Parking Area | 6,066.55 square metres |
| Estimated Power Requirement | 2.0 MW |
| Fresh Water Requirement | 115 kl/day |
| Greenbelt Area | 608.68 square metres |
Layout and design
The layout plan indicates three distinct building blocks. Block A is situated towards the northern boundary, while Blocks B and C are located towards the southern end of the plot. The buildings will include two basement levels for parking, a hollow plinth for additional parking and services, and upper floors for residential and commercial use.
Internal access is provided via 6.00-metre wide approach roads and ramps leading to the basements. The design includes common amenities for society use, a common plot of 420.68 square metres, and dedicated spaces for a sewage treatment plant (STP), underground water tanks, and a diesel generator (DG) set.
Land and surroundings
The project site is located at Final Plot No. 6 of Draft Town Planning Scheme No. 65 (Jagatpur-Tragad-Chandkheda-Chenpur-Ranip) in Tragad. The site is currently open land and is situated within the Ahmedabad Municipal Corporation (AMC) limits.
The surrounding area is primarily residential and commercial. The Sabarmati railway station is approximately 5.5 km away, and the Ahmedabad Airport is about 9.5 km from the site. A railway line and its associated building control line run adjacent to the eastern boundary of the property.
Water, power and access
During the operational phase, the total water requirement is estimated at 168 kl/day for the first day, reducing to a fresh water demand of 115 kl/day thereafter. Water will be sourced from the Ahmedabad Municipal Corporation (Narmada water). The applicant states that if groundwater extraction is required, they will seek permission from the Central Ground Water Authority (CGWA).
Power will be supplied by Uttar Gujarat Vij Company Limited (UGVCL). The estimated demand during the construction phase is 25 kW, rising to 2.0 MW during operations. A DG set is planned for emergency backup. Access to the site is provided by 12.00-metre wide Town Planning Scheme (TPS) roads.
Environmental safeguards
The applicant proposes several environmental management measures:
- Waste Management: A sewage treatment plant (STP) with a capacity of 100 KLD using MBBR (Moving Bed Biofilm Reactor) technology will be installed. Treated water will be reused for flushing and gardening. Solid waste will be segregated; wet waste (approximately 275 kg/day) will be processed in an on-site Organic Waste Converter (OWC), while dry waste (225 kg/day) will be collected by the AMC.
- Rainwater Harvesting: Two percolation wells are planned to recharge ground aquifers.
- Greenbelt: A total green area of 608.68 square metres is proposed, including 188 square metres of tree cover and 420.68 square metres of lawn.
- Energy Conservation: The project includes plans for a 78 kW rooftop solar plant, solar street lights, and the use of LED lighting in common areas. Electric vehicle (EV) charging stations will be provided for 20% of the car parking spaces (43 stations).
- Air and Noise: During construction, tarpaulin covers, water sprinkling, and peripheral barricading with GI sheets will be used to control dust. Equipment will be provided with acoustic enclosures where necessary.
The Saffron site plan and layout
4 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
1,175 applications in Ahmadabad since January 2022 are in the same category (Buildings & townships): 916 approved, 201 filed or under review, and 58 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 0.9 acres, this one is smaller than 88% of them.
174 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Tragad, Sabarmati, Ahmadabad, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Samay Sanidhya — environmental approval granted, 300 m away
- Orium Sylva — initial checks, 450 m away
- The Amber — environmental approval granted, 600 m away
- The Amber — environmental approval granted, 600 m away
- Shree Kalash — environmental approval granted, 650 m away
- Shree Kalash — environmental approval granted, 650 m away
- Wertical Edge — under environmental review, 750 m away
- Million Minds Tech-City (Phase-I) — environmental approval granted, 800 m away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.