What is Aastha Eminence?
Aastha Eminence is a proposed building project in Zundal, Gandhinagar, Gujarat. The site covers 1.8 acres.
Who is building it?
The applicant is Prahladbhai Dahyabhai Prajapati.
Has it been approved?
Not yet. The application is still under review: its status is “Initial checks”, as of 27 Nov 2026.
Where is it?
In Zundal, Gandhinagar, Gujarat.
How big is it?
It has a stated cost of ₹133 crore and a site of 1.8 acres.
When was it filed?
The application was filed on 24 Aug 2026.
Project details
| Status | Initial checks |
|---|---|
| Status since | 19 Oct 2026 |
| Application filed | 24 Aug 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Prahladbhai Dahyabhai Prajapati |
| Land area | 1.8 acres (0.7 ha) |
| Project cost | ₹133 crore |
| Village / locality | Zundal |
| Taluk / tehsil | Gandhinagar |
| District | Gandhinagar |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-11002 |
What the filings say
What is planned
The applicant, Prahladbhai Dahyabhai Prajapati, proposes the construction of a residential project named Aastha Eminence in Zundal, Gandhinagar. The project report describes a residential development consisting of five blocks (A, B, C, D, and E) with a maximum height of 14 floors above a hollow plinth and two cellar levels for parking.
The project is planned to provide a total of 252 residential units. The total built-up area is specified as 58,202.47 square metres, with a total FSI (Floor Space Index) area of 32,622.66 square metres.
Project Components
| Item | Detail |
|---|---|
| Total Residential Units | 252 |
| Number of Blocks | 5 (A, B, C, D, E) |
| Building Height | 2 Cellars + Ground (Hollow Plinth) + 14 Floors |
| Total Built-up Area | 58,202.47 sq. mts. |
| Total FSI Area | 32,622.66 sq. mts. |
| Common Plot Area | 728.04 sq. mts. |
| Proposed Parking Area | 12,036.41 sq. mts. (Cellars) |
Layout and design
The layout plan indicates five distinct building blocks arranged around a central common plot. Blocks B, C, and D appear to be interconnected or clustered, while Blocks A and E are positioned separately. The ground level is designed as a hollow plinth primarily for parking and common amenities.
Access to the buildings is provided via a 7.50-metre wide approach road leading from an 18.00-metre wide Town Planning Scheme (TPS) road. Internal circulation includes 6.00-metre wide roads to ensure smooth vehicle movement. The design incorporates dedicated foyers for each block, multiple staircases, and two lifts per block (one general lift and one fire lift), each with a 13-person capacity.
Land and surroundings
The project is situated on Final Plot No. 88 of TPS No. 72 (Tragad-Zundal), corresponding to Revenue Survey No. 424 (O.P. No. 88) in Zundal village. The total plot area is 7,223 square metres (0.72 hectares). The site is bounded by adjacent final plots on three sides and the 18.00-metre TPS road on the south. The surrounding area is designated as a Residential-2 (R2) zone.
Water, power and access
During the operation phase, the project will require water for domestic use, gardening, and firefighting. The applicant plans to install a Sewage Treatment Plant (STP) with a capacity of 80 KLD (kilolitres per day). Treated sewage will be reused for flushing and gardening within the premises, with any excess discharged into the local municipal drainage line.
Power will be sourced from the local grid, with a 200 KVA Diesel Generator (DG) set proposed for emergency backup. The project includes a rooftop solar energy system with a proposed capacity of 171 KW, utilizing approximately 1,714.25 square metres of terrace space.
Environmental safeguards
The Environmental Management Plan (EMP) outlines measures for dust suppression during construction, including 15-foot high barricading and water sprinkling. For the operation phase, the applicant proposes a greenbelt covering 728.04 square metres, which includes a lawn area of 436.82 square metres and a tree plantation area of 291.22 square metres. A total of 181 trees are planned to be provided on-site, including species such as Asopalav, Neem, Pipal, Gulmohar, and Saptparni.
Rainwater harvesting will be managed through two percolation wells and a collection trench. Solid waste will be segregated at source, with wet waste treated on-site using an organic waste converter (OWC). The project also includes provisions for Electric Vehicle (EV) charging facilities.
Timeline
The applicant's project report states that the entire project is expected to be completed within approximately four years. The installation of environmental management units will proceed in parallel with the building construction.
Aastha Eminence site plan and layout
4 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
472 applications in Gandhinagar since January 2022 are in the same category (Buildings & townships): 365 approved, 79 filed or under review, and 28 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 1.8 acres, this one is larger than 67% of them.
129 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Zundal, Gandhinagar, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Ekayan — environmental approval granted, 200 m away
- Aditya Antilia — environmental approval granted, 450 m away
- Status Sharan — environmental approval granted, 500 m away
- Samhita — environmental approval granted, 650 m away
- The Atlantis 2 — environmental approval granted, 700 m away
- The Satyagrah Residency — environmental approval granted, 700 m away
- The Satyagrah Residency — environmental approval granted, 700 m away
- Vedant Stella — environmental approval granted, 750 m away