Quick answers
What is this project?
Application for grant of TOR and EC Of Existing Rolling Mill under notification S.O. 3250 dated 20.07.2022 ((TMT Steel Rods/Bars (8-50 MM), Round Steel Rods/Bars (6-800 MM), Square Steel Rods/Bars (8-80 MM), Square Steel Rods/Bars (8-80 MM) with Production capacity 311040 TPA) at Survey no. 231/1, 231/2, 232, 233 & 234, Lunva, Taluka: Bhachau, District: Kutch, Gujarat by M/s S. Poddar International (India) Pvt Ltd is a lapsed industrial project in Lunva, Bhachau, Kachchh, Gujarat. The site covers 23.1 acres.
Who is building it?
The applicant is S Poddar International (India) Private Limited.
Has it been approved?
No. The application was lapsed on 5 Jun 2026, so it is no longer under consideration.
Where is it?
In Lunva, Bhachau, Kachchh, Gujarat.
How big is it?
It has a stated cost of ₹60 crore and a site of 23.1 acres.
When was it filed?
The application was filed on 6 Apr 2026.
One of 2 filings for this project. The project's main page, with every filing and where each stands: Application for grant of TOR and EC Of Existing Rolling Mill under notification S.O.…
Project details
| Status | Lapsed |
|---|---|
| Status since | 5 Jun 2026 |
| Application filed | 6 Apr 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | S Poddar International (India) Private Limited |
| Land area | 23.1 acres (9.3 ha) |
| Project cost | ₹60 crore |
| Village / locality | Lunva |
| Taluk / tehsil | Bhachau |
| District | Kachchh |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-11071 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 6 Apr 2026 (this page) | Lapsed | 23.1 acres | ₹60 crore |
| Early planning filed 26 Aug 2023 | Cleared for impact study | 23.1 acres | ₹60 crore |
In context
160 applications in Kachchh since January 2022 are in the same category (Industry): 104 approved, 40 filed or under review, and 16 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 23.1 acres, this one is smaller than 63% of them.
3 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Lunva, Bhachau, Kachchh, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Application for grant of TOR and EC Of Existing Rolling Mill under… — cleared for impact study, 0 m away
- Shri Vikram Gopalbhai Chhanga. — environmental approval granted, 3 km away
- Extension of Environment Clearance(EC) Validity for M/s. Genus Paper and Coke… — environmental approval granted, 3.3 km away
- Shri Valji Naran Kerasiya — lapsed, 4.1 km away
- Proposed Minor Mineral (China Clay) mining Project by Reliance Industries… — environmental approval granted, 5.5 km away
- Proposed Minor Mineral (China Clay) mining Project by Reliance Industries… — environmental approval granted, 6.5 km away
- Proposed Silica Sand Beneficiation Project of Reliance Industries Limited at… — cleared for impact study, 6.7 km away
- Shri Patel Prakashkumar Jadavjibhai — environmental approval granted, 6.8 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.