Project details
| Status | Lapsed |
|---|---|
| Status since | 15 Aug 2026 |
| Application filed | 7 Feb 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Patel Ankit |
| Land area | 9 acres (3.6 ha) |
| Project cost | ₹11 lakh |
| Village / locality | Udalpur |
| Taluk / tehsil | Desar |
| District | Vadodara |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-11155 |
All filings for this project
This project has 4 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 7 Feb 2026 (this page) | Lapsed | 9 acres | ₹11 lakh |
| New project filed 13 Dec 2025 | Under environmental review | 12.2 acres | ₹14.6 crore |
| Early planning filed 13 Dec 2024 | Cleared for impact study | 12.2 acres | ₹14.6 crore |
| New project filed 16 Sept 2024 | Environmental approval granted | 9 acres | ₹9.3 crore |
In context
297 applications in Vadodara since January 2022 are in the same category (Mining): 133 approved, 57 filed or under review, and 107 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 9 acres, this one is larger than 83% of them.
2 other mining leases have applied within 500 m of this site; together with this one they cover 29.6 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 28 mining leases have applied within 5 km.
Where it is
Udalpur, Desar, Vadodara, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Mining project by Prabhu Ispat Pvt Ltd — environmental approval granted, 0 m away
- Mining project by Prabhu Ispat Pvt. Ltd — under environmental review, 250 m away
- Mining project by Prabhu Ispat Pvt. Ltd — cleared for impact study, 250 m away
- Kirankumar Parikh — environmental approval granted, 350 m away
- Kirankumar Parikh — cleared for impact study, 350 m away
- M/s Bhagirath Quarry Works Pvt. Ltd. Re-appraisal of Environment Clearance… — lapsed, 750 m away
- Vijaykumar G Patel (Tulsigam Blacktrap Block-5) — under environmental review, 800 m away
- VIJAYKUMAR G PATEL(Tulsigam Black Trap Quarry Lease Block-7) — under environmental review, 800 m away