Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 21 Jul 2026 |
| Application filed | 22 Apr 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Sorathiya Nitin Damjibhai |
| Use | Mixed use |
| Units | 358 |
| Towers | 5 |
| Floors (tallest) | 14 |
| Basements | 1 |
| Parking spaces | 507 |
| Land area | 2.5 acres (1 ha) |
| Built-up area | 46,972 m² (5,05,602 sq ft) |
| Plot area | 9,956 m² (1,07,165 sq ft) |
| Project cost | ₹53 crore |
| Village / locality | Mavdi |
| Taluk / tehsil | Rajkot |
| District | Rajkot |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-11188 |
What the filings say
What is planned
Arrows one is a residential and commercial construction project proposed by Shri Nitinbhai Damjibhai Sorathiya & Others. The applicant's project reports describe a development consisting of five towers (Tower A to Tower E) that combine housing with retail spaces.
The layout includes a ground floor dedicated to commercial activities, featuring 63 shops ranging in size from 260 sq. ft. to 461 sq. ft. A banquet hall measuring 22’-0— x 55’-9— is also planned for the ground floor. Residential units are distributed across the upper floors, with the project documents showing floor plans up to the 14th floor.
Project Components
| Item | Detail |
|---|---|
| Total Towers | 5 (A, B, C, D, E) |
| Maximum Floors | 14 |
| Commercial Units | 63 shops |
| Ground Floor Amenities | Banquet hall, Security cabin |
| Recreational Facilities | Children play area, Senior citizen park, Jogging track |
Layout and design
The project is situated on a plot bounded by a 24.00-metre wide D.P.T.P. road and a 12.00-metre wide T.P. road. The ground floor serves as the primary commercial hub with shops arranged along the perimeter and internal corridors.
Residential towers are positioned above the commercial base. The design incorporates a central common plot area for residents. Basement levels are designated for vehicle parking, with specific ramps for entry and exit. Each tower is equipped with multiple lifts and dedicated passage areas. The architectural design emphasizes natural ventilation for public areas and the orientation of buildings to maximize daylight.
Land and surroundings
The project is located in Mavdi, Rajkot. The site plan indicates the inclusion of several green and open spaces, including a garden measuring 42’-9— x 59’-9—, a senior citizen park, and a sand pit. A peripheral green belt is planned to be developed with native plant species.
Water, power and access
Water management will involve a combination of fresh water supply and treated wastewater reuse. The applicant proposes to use treated water for landscaping, flushing, and cooling for Diesel Generator (DG) sets. Rainwater harvesting systems will be installed to recharge groundwater.
Power will be supported by DG sets for backup, which will be housed in acoustic enclosures to manage noise. Energy conservation measures include the use of energy-efficient lamps and solar lighting for public areas. Access to the site is provided through the adjacent 24-metre and 12-metre wide roads.
Environmental safeguards
The applicant has submitted an Environment Management Plan (EMP) covering both construction and operation phases:
- Air Quality: Dust suppression using water sprinklers during construction. DG sets will have adequate stack heights for pollutant dispersal.
- Noise Control: Construction activities will be restricted to specific times. Acoustic enclosures for DG sets will ensure noise levels do not exceed 75 dB(A) at 1 metre.
- Waste Management: Construction debris will be recycled where possible. During operation, organic waste converters will treat biodegradable waste, while recyclable materials will be sold to authorized vendors.
- Greenbelt: A total green area of 1,000 square metres is planned, representing approximately 10.04% of the net plot area.
- Water Quality: Septic tanks will be used during construction to prevent wastewater from entering water bodies. A sewage treatment plant is proposed for the operational phase.
Shri Nitinbhai Damjibhai Residential Cum Commercial Building Construction Project Arrows One site plan and layout
4 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
134 applications in Rajkot since January 2022 are in the same category (Buildings & townships): 109 approved, 17 filed or under review, and 8 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 2.5 acres, this one is larger than 71% of them.
81 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Mavdi, Rajkot, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Residential Cum Commercial Project proposed by Shri Shaileshbhai Polabhai… — environmental approval granted, 150 m away
- Proposed Residential cum Commercial Building Project by Shubh Builders — environmental approval granted, 200 m away
- Residential cum Commercial Building Project by SHRIBALAJI SMARTBUILD LLP — environmental approval granted, 200 m away
- Residential cum Commercial Building Project by SHRIBALAJI SMARTBUILD LLP — under environmental review, 200 m away
- Residential Cum Commercial Project proposed by Cubicon Property — environmental approval granted, 350 m away
- Residential Cum Commercial Project proposed by Shree Vallabhbhai Mavjibhai… — environmental approval granted, 350 m away
- Proposed Residential cum Commercial Project Century Regaliya by Shri… — environmental approval granted, 350 m away
- Proposed Residential cum Commercial Project Century Regaliya by Shri… — environmental approval granted, 350 m away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.