Quick answers
What is Jeet Iconic?
Jeet Iconic is a proposed building project in Palaj, Gandhinagar, Gujarat. The site covers 1.6 acres.
Who is building it?
The applicant is Bihola Jaspal P.
Has it been approved?
Not yet. The application is still under review: its status is “Under environmental review”, as of 27 Nov 2026.
Where is it?
In Palaj, Gandhinagar, Gujarat.
How big is it?
It has a stated cost of ₹80 lakh and a site of 1.6 acres.
When was it filed?
The application was filed on 26 Aug 2026.
One of 2 filings for this project. The project's main page, with every filing and where each stands: Jeet Iconic
Project details
| Status | Under environmental review |
|---|---|
| Status since | 7 Oct 2026 |
| Application filed | 26 Aug 2026 |
| Approval sought | Environmental approval |
| Application type | Ownership transfer |
| Sector | Buildings & townships |
| Applicant | Bihola Jaspal P |
| Land area | 1.6 acres (0.6 ha) |
| Project cost | ₹80 lakh |
| Village / locality | Palaj |
| Taluk / tehsil | Gandhinagar |
| District | Gandhinagar |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-11190 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Ownership transfer filed 26 Aug 2026 (this page) | Under environmental review | 1.6 acres | ₹80 lakh |
| New project filed 21 May 2025 | Environmental approval granted | 1.6 acres | ₹80 lakh |
What the filings say
What is planned
Jeet Iconic is a residential and commercial development proposed by Jaspal P. Bihola in Palaj, Gandhinagar. The applicant's project report describes a multi-block complex combining affordable housing, hostel facilities, and retail shops.
The project consists of four main building blocks (A, B, C, and D) with a maximum height of 14 floors above ground level. The total proposed built-up area is 31,977.60 square metres. The residential component includes 182 units of affordable housing. The commercial segment is located on the ground floor, featuring various shops.
Building Configuration
| Block | Floors | Use |
|---|---|---|
| Block A | Basement + Hollow Plinth + 14 Floors | Residential |
| Block B | Basement + Hollow Plinth + 14 Floors | Residential |
| Block C | Basement + Hollow Plinth + 14 Floors | Residential + Hostel |
| Block D | Basement + Hollow Plinth + 14 Floors | Residential + Hostel |
Layout and design
The project is situated on a plot of 0.63 hectares (1.56 acres). The layout includes two common plots totaling 638.60 square metres. The buildings are arranged around a central 6.00-metre wide internal road system that provides access to all blocks and the basement ramp.
Parking is provided across the basement and hollow plinth levels. The first basement covers 4,908.12 square metres. The ground floor hollow plinth areas are designated for both residential and commercial parking, including dedicated visitor parking spaces.
Water, power and access
During the construction phase, water will be sourced from local water tanker suppliers under the Gandhinagar Urban Development Authority (GUDA). For the operation phase, water will be supplied directly by GUDA. The applicant proposes to install a water metering system and low-flow fixtures, such as diffused water taps and twin flushing systems, to reduce consumption.
Power will be supported by Diesel Generator (DG) sets for emergency backup. These will be equipped with acoustic enclosures and stack heights following Central Pollution Control Board (CPCB) norms. Energy conservation measures include the use of LED lighting in common areas, solar lights in open areas, and a rooftop solar system with a capacity of 100 KW.
Environmental safeguards
The applicant's Environmental Management Plan (EMP) outlines several mitigation measures:
- Wastewater: Domestic sewage will be treated in a Moving Bed Biofilm Reactor (MBBR) type Sewage Treatment Plant (STP) with a capacity of 200 kilolitres per day (KLD). The STP will occupy approximately 100 square metres.
- Solid Waste: An automatic Organic Waste Converter (OWC) with a capacity of 300 kg/day will be installed to process wet waste into compost for greenbelt development. Other municipal solid waste will be segregated and collected by GUDA.
- Air and Noise: Dust mitigation during construction includes water sprinkling and peripheral barricading. Construction activities involving high noise levels will be restricted to daytime.
- Rainwater Harvesting: The project includes a collection system with two percolating wells to recharge the groundwater table.
- Greenbelt: A total of 159 trees are planned to be planted on-site, covering the required green area.
Project Costs
The total capital cost for the Environmental Management Plan is estimated at ₹463.70 lakh, with an annual recurring cost of ₹26.85 lakh. This includes ₹185.40 lakh for fire and safety systems and ₹55.00 lakh for solar energy installations.
Jeet Iconic site plan and layout
4 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
472 applications in Gandhinagar since January 2022 are in the same category (Buildings & townships): 365 approved, 79 filed or under review, and 28 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 1.6 acres, this one is larger than 57% of them.
41 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Palaj, Gandhinagar, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Jeet Iconic — environmental approval granted, 0 m away
- Construction Work (as approved in earlier EC) at Indian Institute of… — environmental approval granted, 700 m away
- Construction Work (as approved in earlier EC) at Indian Institute of… — cleared for impact study, 700 m away
- Stavya Sky — environmental approval granted, 750 m away
- Foresta — more information requested, 1.5 km away
- Foresta — environmental approval granted, 1.5 km away
- Drilling of 5-10 Development Well in Indroda Oil Field Block Cambay Basin,… — lapsed, 2.2 km away
- EC Transfer for the drilling of 5-10 development wells in Indrora Oil Field… — environmental approval granted, 2.2 km away
About this information