Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 16 May 2026 |
| Application filed | 2 Jan 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Riviera Infraspace LLP |
| Use | Residential |
| Units | 320 |
| Towers | 4 |
| Floors (tallest) | 21 |
| Basements | 3 |
| Height | 70 m |
| Parking spaces | 980 |
| Land area | 3.1 acres (1.2 ha) |
| Built-up area | 1,06,308 m² (11,44,289 sq ft) |
| Plot area | 12,424 m² (1,33,731 sq ft) |
| Project cost | ₹195 crore |
| Village / locality | Sarkhej-Okaf |
| Taluk / tehsil | Sabarmati |
| District | Ahmadabad |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-11249 |
What the filings say
The applicant, Riviera Infraspace LLP, proposes to develop a new residential project named Riviera Arista in Ahmadabad. According to the project reports, the development will consist of 320 residential units distributed across four building blocks, designated as Block A, Block B, Block C, and Block D.
The buildings are designed to reach a height of 69.95 metres from ground level to the terrace. Each block is planned with a ground floor and 21 upper floors. The project also includes three basement levels for parking and services.
Layout and Design
The project is situated on an amalgamated plot of 1.24 hectares (3.06 acres). The layout includes a total built-up area of 1,06,307.97 square metres. The building blocks are arranged around common plots and open spaces as follows:
- Block A: 80 units.
- Blocks B and C: 160 units (80 units each).
- Block D: 80 units.
A society common facility building is planned within the common plot area, featuring amenities such as a swimming pool (16.80m x 4.95m), a gymnasium, and community spaces. The total area provided for common plots is 2,661.97 square metres.
Land and Surroundings
The site is located at Final Plot No. 101 and 114/2 within Draft Town Planning Scheme No. 86 (Sarkhej-Okaf-Fatehwadi-Makarba). Geotechnical investigations conducted at the site found the ground water table at a depth of 18.0 metres below the existing ground level. The soil profile consists of stiff dark brown clayey silt near the surface, transitioning to medium to dense silty sand and hard brown clayey sand at greater depths. The report recommends the use of isolated column footings or raft foundations for the structures.
Water, Power and Access
During the operation phase, the project will require 316.47 kilolitres per day (KLD) of water. This includes a fresh water requirement of 211.5 KLD and a treated wastewater requirement of 104.97 KLD for flushing and horticulture. For the construction phase, the total water requirement is estimated at 14.5 KLD.
Power will be sourced from the local grid, with a total connected load of approximately 1,280 kW. The applicant plans to install rooftop solar energy panels to generate 64 kW, meeting approximately 5% of the connected load requirement. Access to the site is provided via a 30-metre wide Town Planning Scheme (TPS) road and a 12-metre wide TPS road.
Environmental Safeguards
The applicant has proposed an Environmental Management Plan with a capital budget of ₹133.5 lakh and an annual recurring budget of ₹13.5 lakh. Key safeguards include:
- Wastewater Treatment: A Sewage Treatment Plant (STP) with a capacity of 270 KLD will be installed. Treated water will be reused for flushing and gardening.
- Rainwater Harvesting: Four percolation wells are planned to recharge groundwater, with an estimated annual recharge capacity of 5,020 cubic metres.
- Greenbelt: The plan includes planting 311 trees within the premises.
- Solid Waste: Organic waste will be segregated and converted into compost using an on-site organic waste converter.
Fire and Safety
Fire protection facilities will be designed as per the National Building Code. Planned infrastructure includes a 2,00,000-litre underground static water storage tank and a 20,000-litre terrace tank. The buildings will be equipped with wet risers, yard hydrants, automatic sprinkler systems in the basements, and fire lifts.
| Item | Detail |
|---|---|
| Total Residential Units | 320 |
| Number of Blocks | 4 |
| Maximum Building Height | 69.95 metres |
| Total Built-up Area | 1,06,307.97 square metres |
| STP Capacity | 270 KLD |
| Solar Power Generation | 64 kW |
| Tree Plantation | 311 trees |
| Basements | 3 levels |
Riviera Arista site plan and layout
4 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
1,175 applications in Ahmadabad since January 2022 are in the same category (Buildings & townships): 916 approved, 201 filed or under review, and 58 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 3.1 acres, this one is larger than 79% of them.
203 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Sarkhej-Okaf, Sabarmati, Ahmadabad, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Orchid Regal — environmental approval granted, 200 m away
- Riviera Prestige — environmental approval granted, 200 m away
- Ninety — environmental approval granted, 750 m away
- Aurelius — under environmental review, 850 m away
- Ombre — environmental approval granted, 900 m away
- Prive 88 — environmental approval granted, 950 m away
- Prive 88 — environmental approval granted, 950 m away
- Prive 88 — environmental approval granted, 950 m away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.