Project details
| Official title | Proposal for protected forest land of 0.50575 Ha. to be used for laying of 66kV S/C, 1CX630 Sq.mm. (3+1 Spare), total 04 nos. of Underground Electric Power Cable Line by laying parallel (Along) to Nandpur-Bharatpur State Highway No. 175 Road(Baska – Rameshra Road between KM CH:3/800 to 9/650) near Village: Vasenti, Ghansar, Muvadi, Vanta, Medi & Madar, Ta.:Halol, Dist.: Panchmahal in respect of 66kV Madar – M/s. Polycab India Pvt. Ltd. line proposed from GETCO's existing 66kV Madar Substation to |
|---|---|
| Status | Forest land use approved |
| Status since | 11 Sept 2026 |
| Application filed | 12 May 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Gujarat Energy Transmission Corp LTD |
| Forest land | 1.3 acres (0.5 ha) |
| Project cost | ₹2.6 crore |
| Village / locality | Ghansar |
| Taluk / tehsil | Halol |
| District | Panch Mahals |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-12053 |
In context
5 applications in Panch Mahals since January 2022 are in the same category (Power): 2 approved, 3 filed or under review, and 0 withdrawn, lapsed or rejected.
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Ghansar, Halol, Panch Mahals, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Diversion of 0.47971Ha. protected forest land for laying of 66 kv Under Ground… — lapsed, 2.4 km away
- Diversion of 0.1150 Ha. Reserved Forest land for Construction of Tajpura… — not approved, 5.1 km away
- Patel Associates [Lease 4.00 Hacters] — environmental approval granted, 5.6 km away
- Shri Bhogilal Madhavbhai Patel Reapprasial Area 1.00.00Village-Gopipura,Taluka-… — lapsed, 5.7 km away
- Shri Bhogilal Madhavbhai Patel (Re-Appraisal) Lease Area-1.00.00Ha. Vill:… — environmental approval granted, 5.7 km away
- Shri Bharat Govindbhai Bharvad (Gopipura Black Trap Block No- 5) — under environmental review, 5.9 km away
- Shri Bharat Govindbhai Bharvad (Gopipura Block- 5) — lapsed, 5.9 km away
- Change in Product Mix for Alembic Pharmaceuticals Ltd., API Unit – 2, Vill.… — initial checks, 5.9 km away
More from Gujarat Energy Transmission Corp LTD in Panch Mahals
- Diversion of 0.0044 Ha Protected Forest Land for the 66 KV Nandarkha LILO line… — more information requested
- Diversion of 0.0184 Ha Forest Land for the 66 KV Nandarkha LILO line from the… — more information requested
- Protected forest land of 0.41921 Ha. to be used for laying of 66kV D/C, 1CX630… — under forest review
- Diversion of 0.47971Ha. protected forest land for laying of 66 kv Under Ground… — lapsed
- Diversion of 0.9252 Ha. of Reserved forest land for 66 KV S/C Saudas na Muvada… — forest land use approved
6 Gujarat Energy Transmission Corp projects in Panch Mahals
All 231 Gujarat Energy Transmission Corp projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.