Quick answers
What is this project?
Diversion of 0.075 Ha Reserved Forest Land of Kutch (West) Forest Division of Overhead 33 KV Transmission Line for the 145.2 MW Ayana Nakhatrana-Bhuj wind power project is a lapsed power project in Virani Nani, Nakhatrana, Kachchh, Gujarat. The site covers 63.2 acres.
Who is building it?
The applicant is Kpi Green Energy Limited.
Has it been approved?
No. The application was lapsed on 20 Feb 2026, so it is no longer under consideration.
Where is it?
In Virani Nani, Nakhatrana, Kachchh, Gujarat.
How big is it?
It has a stated cost of ₹1.5 crore; a site of 63.2 acres and 750 m² of forest land.
When was it filed?
The application was filed on 20 Jan 2026.
Project details
| Status | Lapsed |
|---|---|
| Status since | 20 Feb 2026 |
| Application filed | 20 Jan 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Kpi Green Energy Limited |
| Land area | 63.2 acres (25.6 ha) |
| Forest land | 750 m² |
| Project cost | ₹1.5 crore |
| Village / locality | Virani Nani |
| Taluk / tehsil | Nakhatrana |
| District | Kachchh |
| State | Gujarat |
| Location from | Site area on record |
| Our reference | WID-GJ-12424 |
In context
75 applications in Kachchh since January 2022 are in the same category (Power): 30 approved, 30 filed or under review, and 11 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 63.2 acres, this one is larger than 66% of them.
37 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Virani Nani, Nakhatrana, Kachchh, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Diversion of 0.8526 Ha Forest land for the laying of Proposed Underground… — lapsed, 1.6 km away
- Proposed for Laying of Proposed Underground Water Pipeline in Favor of Gwssb… — more information requested, 1.6 km away
- Ashish Kumar Singh — lapsed, 4 km away
- Ashish Kumar Singh — cleared for impact study, 4 km away
- Vijaysinh Narendrasinh Parmar (Kotda Jadodar Blacktrap Block - J) — under environmental review, 4.1 km away
- Azaz Amad Khalifa — environmental approval granted, 4.2 km away
- Azaz Amad Khalifa — cleared for impact study, 4.2 km away
- Khambhala Blacktrap Bl0ck-8 — cleared for impact study, 4.3 km away
More from Kpi Green Energy Limited in Kachchh
- Diversion of 0.03 Ha. Protected forest land of Kutch Social Forestry Division… — forest land use approved