What is Developing? Open the mapMap

Forest land use approvedPipelines · Surendranagar, Gujarat

Proposed laying of 36" dia. Steel underground crude oil Pipeline across the Lakhtadividi Reserved Forest by BPCL

Proposed laying of 36" dia. Steel underground crude oil Pipeline across the Lakhtadividi Reserved Forest by BPCL is an approved pipeline project in Chitralank, Sayla, Surendranagar, Gujarat. The site covers 16.4 acres. Its stated project cost is ₹5 crore. As of 27 Nov 2026, its status is “Forest land use approved” (since 24 Sept 2026).

See it on the live map All projects in Surendranagar

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Proposed laying of 36" dia. Steel underground crude oil Pipeline across the Lakhtadividi Reserved Forest by BPCL is an approved pipeline project in Chitralank, Sayla, Surendranagar, Gujarat. The site covers 16.4 acres.

Who is building it?

The applicant is Bharat Petroleum Corporation Limited (BPCL).

Has it been approved?

Yes. Its status is “Forest land use approved” (since 24 Sept 2026), as of 27 Nov 2026.

Where is it?

In Chitralank, Sayla, Surendranagar, Gujarat.

How big is it?

It has a stated cost of ₹5 crore; a site of 16.4 acres and 2.4 acres (1 ha) of forest land.

When was it filed?

The application was filed on 2 Jan 2026.

Project details

Official titleProposed laying of 36" dia. Steel underground crude oil Pipeline across the Lakhtadividi Reserved Forest in Chorvira Village for Vadinar - Bina Pipeline Capacity Augmentation Project in Surendranagar District
StatusForest land use approved
Status since24 Sept 2026
Application filed2 Jan 2026
Approval soughtForest land use
Application typeNew project
SectorPipelines
ApplicantBharat Petroleum Corporation Limited (BPCL)
Land area16.4 acres (6.7 ha)
Forest land2.4 acres (1 ha)
Project cost₹5 crore
Village / localityChitralank
Taluk / tehsilSayla
DistrictSurendranagar
StateGujarat
Location fromSite boundary on record
Our referenceWID-GJ-13131

In context

26 applications in Surendranagar since January 2022 are in the same category (Pipelines): 16 approved, 9 filed or under review, and 1 withdrawn, lapsed or rejected. The approved ones took a median of 19 months from filing to approval. At 16.4 acres, this one is larger than 96% of them.

51 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Chitralank, Sayla, Surendranagar, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Bharat Petroleum Corporation Limited (BPCL) in Surendranagar

All 656 Bharat Petroleum Corporation (BPCL) projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.