Forest land use approvedPower · Kachchh, Gujarat

Diversion of 0.026 Ha. Protected forest land of Kutch Social Forestry Division for construction of 33 KV Overhead Transmission line in-favor of Ayana Renewable Power Four Private Limited.

Diversion of 0.026 Ha. Protected forest land of Kutch Social Forestry Division for construction of 33 KV Overhead Transmission line in-favor of Ayana Renewable Power Four Private Limited is an approved power project in Sukhpar (Virani), Nakhatrana, Kachchh, Gujarat. The site covers 0.1 acres. Its stated project cost is ₹50 lakh. As of 27 Nov 2026, its status is “Forest land use approved” (since 25 Jul 2025).

See it on the live map All projects in Kachchh

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Diversion of 0.026 Ha. Protected forest land of Kutch Social Forestry Division for construction of 33 KV Overhead Transmission line in-favor of Ayana Renewable Power Four Private Limited is an approved power project in Sukhpar (Virani), Nakhatrana, Kachchh, Gujarat. The site covers 0.1 acres.

Who is building it?

The applicant is Ayana Renewable Power Four Private Limited.

Has it been approved?

Yes. Its status is “Forest land use approved” (since 25 Jul 2025), as of 27 Nov 2026.

Where is it?

In Sukhpar (Virani), Nakhatrana, Kachchh, Gujarat.

How big is it?

It has a stated cost of ₹50 lakh; a site of 0.1 acres and 260 m² of forest land.

When was it filed?

The application was filed on 13 Jul 2025.

Project details

StatusForest land use approved
Status since25 Jul 2025
Application filed13 Jul 2025
Approval soughtForest land use
Application typeNew project
SectorPower
ApplicantAyana Renewable Power Four Private Limited
Land area300 m²
Forest land260 m²
Project cost₹50 lakh
Village / localitySukhpar (Virani)
Taluk / tehsilNakhatrana
DistrictKachchh
StateGujarat
Location fromSite boundary on record
Our referenceWID-GJ-13929

In context

75 applications in Kachchh since January 2022 are in the same category (Power): 30 approved, 30 filed or under review, and 11 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 0.1 acres, this one is smaller than 97% of them.

9 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Sukhpar (Virani), Nakhatrana, Kachchh, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Ayana Renewable Power Four Private Limited in Kachchh

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.