FCA Permission - laying 11KV three (3-Nos.) Power Cable Transmission Line on SH–80 (Velda-Nijhar), Taluka Nijhar, Dist- Tapi, on route from 11KV Cables from KPIGEL Solar Pooling Sub-Station to GETCO 66 KV Nijhar, Dist-Tapi- Diversion of Protected Forest Area: 0.0472 Ha is an approved power project in Nijhar, Nizar, Tapi, Gujarat. The site covers 0.1 acres.
Who is building it?
The applicant is Kpi Green Energy Limited.
Has it been approved?
Yes. Its status is “Forest land use approved” (since 2 Apr 2025), as of 27 Nov 2026.
Where is it?
In Nijhar, Nizar, Tapi, Gujarat.
How big is it?
It has a stated cost of ₹5 lakh; a site of 0.1 acres and 470 m² of forest land.
When was it filed?
The application was filed on 1 Dec 2024.
Project details
| Status | Forest land use approved |
|---|---|
| Status since | 2 Apr 2025 |
| Application filed | 1 Dec 2024 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Kpi Green Energy Limited |
| Land area | 500 m² |
| Forest land | 470 m² |
| Project cost | ₹5 lakh |
| Village / locality | Nijhar |
| Taluk / tehsil | Nizar |
| District | Tapi |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-14327 |
In context
11 applications in Tapi since January 2022 are in the same category (Power): 2 approved, 2 filed or under review, and 7 withdrawn, lapsed or rejected.
3 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Nijhar, Nizar, Tapi, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Shri Bhumit Yogeshkumar Masrani & Shri Shah Parth Rajnikant — not approved, 3.7 km away
- Manojbhai Bharatbhai Padvi-3.00 Ha. (Ashrava) — not approved, 3.9 km away
- Chhayaben Manojbhai Padvi — not approved, 4 km away
- Manojbhai Bharatbhai Padvi 1.00 New — not approved, 5.6 km away
- Manojbhai Bharatbhai Padvi (03.00.00) — not approved, 6.1 km away
- Diversion of Forest Land 2.1463ha for Jakhvav to Selamba to Akkalkuva OFC… — more information requested, 6.4 km away
- Shri Narendrasinh Nagarbhai Barad, Re-appraisal of Environment Clearance… — lapsed, 6.6 km away
- Jayesh Ashokbhai Rathva — lapsed, 8.2 km away
More from Kpi Green Energy Limited in Tapi
- FCA Proposal of diversion of Forest Area 0.0285 Ha to set up Solar Park — forest land use approved
All 37 Kpi Green Energy projects across India