Quick answers
What is this project?
Diversion of 0.05832 -hectare Reserved forest land for Laying of 66KV S/C Kuvadiya–Vadatra line with 66KV, 1Cx1600sq.mm XLPE Power Cable (3+1) near village Kuvadiya Tal. Khambhaliya & Dist. Devbhumi Dwarka is a lapsed power project in Hansthal, Khambhalia, Devbhumi Dwarka, Gujarat. The site covers 0.1 acres.
Who is building it?
The applicant is Gujarat Energy Transmission Corp LTD.
Has it been approved?
No. The application was lapsed on 3 Aug 2026, so it is no longer under consideration.
Where is it?
In Hansthal, Khambhalia, Devbhumi Dwarka, Gujarat.
How big is it?
It has a stated cost of ₹9.8 crore; a site of 0.1 acres and 580 m² of forest land.
When was it filed?
The application was filed on 7 Jan 2025.
Project details
| Official title | Proposal for diversion of 0.05832 -hectare Reserved forest land for Laying of 66KV S/C Kuvadiya–Vadatra line with 66KV, 1Cx1600sq.mm XLPE Power Cable (3+1) near village Kuvadiya Tal. Khambhaliya & Dist. Devbhumi Dwarka |
|---|---|
| Status | Lapsed |
| Status since | 3 Aug 2026 |
| Application filed | 7 Jan 2025 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Gujarat Energy Transmission Corp LTD |
| Land area | 600 m² |
| Forest land | 580 m² |
| Project cost | ₹9.8 crore |
| Village / locality | Hansthal |
| Taluk / tehsil | Khambhalia |
| District | Devbhumi Dwarka |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-14329 |
In context
21 applications in Devbhumi Dwarka since January 2022 are in the same category (Power): 4 approved, 3 filed or under review, and 14 withdrawn, lapsed or rejected. At 0.1 acres, this one is smaller than 94% of them.
4 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Hansthal, Khambhalia, Devbhumi Dwarka, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Diversion of Forest land for Laying of 66KV S/C Kuvadiya–Vadatra line with… — more information requested, 2 km away
- Laying of 66KV S/C Kuvadiya–Vadatra line with 66KV, 1Cx1600sq.mm XLPE Power… — lapsed, 2.1 km away
- Jayesh M Ravaliya (Kuvadiya Hard Murrum Block- A) — environmental approval granted, 4 km away
- Shri Amitbhai Jesabhai Goriya Reapprasial Area-1.38.93Pvt. land & Survey no.-… — environmental approval granted, 4.4 km away
- Kandoriya Samatbhai Lakhmanbhai. — initial checks, 7 km away
- Shri Devshibhai Arjanbhai Der Reappraisal Area-2.00.00 Govt land & Survey no.-… — environmental approval granted, 7.9 km away
- Diversion of 0.7476 ha Forest land for Laying of 66kV S/C Bhadthar-Ramnagar… — under forest review, 10.5 km away
- Pipeline Project — lapsed, 11.1 km away
More from Gujarat Energy Transmission Corp LTD in Devbhumi Dwarka
- Diversion of 0.0305 Ha Social Forest land for Laying of 66KV LILO Bhankhokhari… — lapsed
- Diversion of Forest land for laying of 66kV D/C Jasapar Satapar line with… — lapsed
- Diversion of 0.67184 Ha Social Forest Land for Laying of 66KV D/C Bhatia… — in-principle approval, conditions pending
- Diversion of 0.7476 ha Forest land for Laying of 66kV S/C Bhadthar-Ramnagar… — under forest review
- Diversion of Forest land for Laying of 66KV S/C Kuvadiya–Vadatra line with… — more information requested
- diversion of 0.3852 -hectare Reserved Forest land for 66KV D/C LINE FROM 66kV… — lapsed
8 Gujarat Energy Transmission Corp projects in Devbhumi Dwarka
All 231 Gujarat Energy Transmission Corp projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.