Quick answers
What is this project?
Mining of Sand, Stone & Bajri Project from Haroti Khad situated in Mauza Lambagaon, Mohal Tikkri Ghumarnu Proposed by, Sh. Vijay Kumar is an approved mining project in Tikri Ghamarrnun (590), Jaisinghpur, Kangra, Himachal Pradesh. The site covers 3.5 acres.
Who is building it?
The applicant is Vijay Kumar.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 18 Oct 2024), as of 27 Nov 2026.
Where is it?
In Tikri Ghamarrnun (590), Jaisinghpur, Kangra, Himachal Pradesh.
How big is it?
It has a stated cost of ₹20 lakh and a site of 3.5 acres.
When was it filed?
The application was filed on 14 Aug 2024.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 18 Oct 2024 |
| Application filed | 14 Aug 2024 |
| Approval sought | Environmental approval |
| Application type | Validity extension |
| Sector | Mining |
| Applicant | Vijay Kumar |
| Land area | 3.5 acres (1.4 ha) |
| Project cost | ₹20 lakh |
| Village / locality | Tikri Ghamarrnun (590) |
| Taluk / tehsil | Jaisinghpur |
| District | Kangra |
| State | Himachal Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-HP-00325 |
In context
131 applications in Kangra since January 2022 are in the same category (Mining): 91 approved, 25 filed or under review, and 15 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 3.5 acres, this one is smaller than 90% of them.
No other mining lease on record is within 500 m of this site; 7 have applied within 5 km.
Where it is
Tikri Ghamarrnun (590), Jaisinghpur, Kangra, Himachal Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Extension in the validity of Environmental Clearance for Extraction/collection… — environmental approval granted, 1.3 km away
- Extension in the validity of Environmental Clearance for Extraction/collection… — environmental approval granted, 1.4 km away
- Extraction/collection of Sand, Stone and Bajri by Shri Udesh Kumar S/o Shri… — environmental approval granted, 2.1 km away
- Extension of EC validity proposal for extraction Sand, Stone & Bajri from… — environmental approval granted, 3 km away
- Extraction of Sand, Stone and Bajri from Khasra No.'s. 1326/2 and 1325/1… — environmental approval granted, 3 km away
- Extraction of Sand, Stone and Bajri from Khasra No. 75 (Private Land, River… — environmental approval granted, 3.3 km away
- Extraction of Stone, Sand and Bajri falling in, Mohal Kutballa, Mauza… — environmental approval granted, 3.3 km away
- Extraction of Sand, Stone, & Bajri from Khasra no, 29 & 31, Measuring an area… — environmental approval granted, 5.6 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.