Cleared for impact studyMining · Una, Himachal Pradesh

Extraction of Sand, Stone and Bajri from Khasra Nos. 596 & 599 over an area measuring 02-47-13 Ha (Pvt. Land- Hill Slope) falling in Mauza/ Mohal Sanjhot, Tehsil & District Una, Himachal Pradesh by Sh. Bhupinder Thakur, Prop. M/s Shiva Stone Crusher

Extraction of Sand, Stone and Bajri from Khasra Nos. 596 & 599 over an area measuring 02-47-13 Ha (Pvt. Land- Hill Slope) falling in Mauza/ Mohal Sanjhot, Tehsil & District Una, Himachal Pradesh by Sh. Bhupinder Thakur, Prop. M/s Shiva Stone Crusher is a proposed mining project in Ambe Da Behra (6/2), Bangana, Una, Himachal Pradesh. The site covers 6.1 acres. Its stated project cost is ₹25 lakh. As of 27 Nov 2026, its status is “Cleared for impact study” (since 26 May 2025).

See it on the live map All projects in Una

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

One of 2 filings for this project. The project's main page, with every filing and where each stands: Extraction of Sand, Stone and Bajri from Khasra Nos. 596 & 599 over an area measuring…

Project details

StatusCleared for impact study
Status since26 May 2025
Application filed25 Feb 2025
Approval soughtEnvironmental approval
Application typeEarly planning
SectorMining
ApplicantBhupinder Thakur
Land area6.1 acres (2.5 ha)
Project cost₹25 lakh
Village / localityAmbe Da Behra (6/2)
Taluk / tehsilBangana
DistrictUna
StateHimachal Pradesh
Location fromSite boundary on record
Our referenceWID-HP-00416

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
New project filed 22 Dec 2025Environmental approval granted6.1 acres₹25 lakh
Early planning filed 25 Feb 2025 (this page)Cleared for impact study6.1 acres₹25 lakh

In context

127 applications in Una since January 2022 are in the same category (Mining): 105 approved, 14 filed or under review, and 8 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 6.1 acres, this one is smaller than 71% of them.

4 other mining leases have applied within 500 m of this site; together with this one they cover 34.8 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 4 mining leases have applied within 5 km.

Where it is

Ambe Da Behra (6/2), Bangana, Una, Himachal Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.