| Status | Lapsed |
|---|---|
| Status since | 26 Feb 2026 |
| Application filed | 5 Jan 2024 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Water & irrigation |
| Applicant | Jamdagni Rishi Hydro Power |
| Land area | 5 acres (2 ha) |
| Forest land | 1.6 acres (0.6 ha) |
| Project cost | ₹11 crore |
| Village / locality | Manikarn (40/101) |
| Taluk / tehsil | Bhuntar |
| District | Kullu |
| State | Himachal Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-HP-02120 |
In context
28 applications in Kullu since January 2022 are in the same category (Water & irrigation): 0 approved, 9 filed or under review, and 19 withdrawn, lapsed or rejected. At 5 acres, this one is smaller than 52% of them.
5 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Manikarn (40/101), Bhuntar, Kullu, Himachal Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Lower Brahamganga-II (0.30 MW) SHEP — under forest review, 3.2 km away
- Kasol Hydro Power Project — lapsed, 3.2 km away
- Jail Hydro 100 KW — lapsed, 3.7 km away
- Lower Balargha (14.00 MW) HEP — more information requested, 4.5 km away
- 132kV D/C Transmission Line from 33/132 KV GIS Sub- Station Barsaini to… — more information requested, 4.5 km away
- Grahan Kasol (5.00 MW) SHEP — more information requested, 5.8 km away
- Grahan Kasol Hydro Power — lapsed, 5.8 km away
- Upper Raskat SHEP (2.00 MW) — under forest review, 6 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.