One of 4 filings for this project. The project's main page, with every filing and where each stands: Proposed 150 KLD Grain based Fuel Ethanol Distillery Plant under EBP program by M/s K2…
Project details
| Official title | Proposed 150 KLD Grain based Fuel Ethanol Distillery Plant under EBP program at Village & P.O. - Goria, Tehsil – Matanhail District – Jhajjar, Haryana by M/s K2 Ethanol Pvt. Ltd. |
|---|---|
| Status | Returned to applicant |
| Status since | 18 Jul 2025 |
| Application filed | 20 Jun 2025 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | K2 Ethanol Private Limited |
| Land area | 15.2 acres (6.2 ha) |
| Project cost | ₹360.1 crore |
| Village / locality | Goria |
| Taluk / tehsil | Kosli |
| District | Rewari |
| State | Haryana |
| Location from | Site area on record |
| Our reference | WID-HR-00713 |
All filings for this project
This project has 4 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 19 Jul 2025 | Environmental approval granted | 15.2 acres | ₹360.1 crore |
| New project filed 20 Jun 2025 (this page) | Returned to applicant | 15.2 acres | ₹360.1 crore |
| Amendment filed 15 Apr 2025 | Returned to applicant | 15.2 acres | ₹360.1 crore |
| Early planning filed 18 Sept 2024 | Cleared for impact study | 15.2 acres | ₹360.1 crore |
In context
15 applications in Rewari since January 2022 are in the same category (Industry): 7 approved, 4 filed or under review, and 4 withdrawn, lapsed or rejected. The approved ones took a median of 31 days from filing to approval. At 15.2 acres, this one is larger than 67% of them.
8 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Goria, Kosli, Rewari, Haryana. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed 150 KLD Grain based Fuel Ethanol Distillery Plant under EBP program — withdrawn, 0 m away
- Proposed 150 KLD Grain based Fuel Ethanol Distillery Plant under EBP program… — returned to applicant, 0 m away
- Proposed 150 KLD Grain based Fuel Ethanol Distillery Plant under EBP program… — environmental approval granted, 100 m away
- Proposed 150 KLD Grain based Fuel Ethanol Distillery Plant under EBP program… — cleared for impact study, 100 m away
- Laying of Water Pipe Line Form Chiriya Minor to Water Works Khursid Nagar on… — lapsed, 600 m away
- Diversion of Forest land for approach access to proposed Retail Outlet of IOCL… — forest land use approved, 3.6 km away
- Diversion of Forest land for approach access to Retail Outlet of IOCL on Kosli… — forest land use approved, 3.8 km away
- RETAIL OUTLET OF HPCLtd. ON SH-22, (KOSLI-KANINA ROAD) AT KM. 66.385, R/SIDE — forest land use approved, 3.8 km away
More from K2 Ethanol Private Limited in Rewari
All 5 K2 Ethanol projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.