Environmental approval grantedBuildings & townships · Gurugram, Haryana

Group Housing Colony Under Retirement Housing Policy over an area of 1.69375 acres/6854.352 sqm (Built-up Area: 24,128.04 Sqm) at Kila No. 18 & 23/1 of Village Sikanderpur Badha, Sector 84, Manesar Tehsil, District Gurugram, Haryana by M/s Lamose Infra LLP

Group Housing Colony Under Retirement Housing Policy over an area of 1.69375 acres/6854.352 sqm (Built-up Area: 24,128.04 Sqm) at Kila No. 18 & 23/1 of Village Sikanderpur Badha, Sector 84, Manesar Tehsil, District Gurugram, Haryana by M/s Lamose Infra LLP is an approved residential project in Badha, Manesar, Gurugram, Haryana. It plans 2 towers of up to 21 floors on 1.7 acres. Its stated project cost is ₹227.7 crore. As of 27 Nov 2026, its status is “Environmental approval granted” (since 21 Aug 2026).

See it on the live map All projects in Gurugram

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Project details

Official titleDevelopment of Group Housing Colony Under Retirement Housing Policy over an area of 1.69375 acres/6854.352 sqm (Built-up Area: 24,128.04 Sqm) at Kila No. 18 & 23/1 of Village Sikanderpur Badha, Sector 84, Manesar Tehsil, District Gurugram, Haryana by M/s Lamose Infra LLP
StatusEnvironmental approval granted
Status since21 Aug 2026
Application filed11 Feb 2026
Approval soughtEnvironmental approval
Application typeNew project
SectorBuildings & townships
ApplicantLamose Infra LLP
UseResidential
Towers2
Floors (tallest)21
Height77 m
Parking spaces190
Land area1.7 acres (0.7 ha)
Built-up area24,128 m² (2,59,711 sq ft)
Plot area6,854 m² (73,776 sq ft)
Project cost₹227.7 crore
Village / localityBadha
Taluk / tehsilManesar
DistrictGurugram
StateHaryana
Location fromSite boundary on record
Our referenceWID-HR-01031

In context

747 applications in Gurugram since January 2022 are in the same category (Buildings & townships): 530 approved, 126 filed or under review, and 91 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 1.7 acres, this one is smaller than 97% of them.

194 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Badha, Manesar, Gurugram, Haryana. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.