Quick answers
What is CGS Station Kushumbhi to Lali Dhaba Connectivity. SFM-GA?
CGS Station Kushumbhi to Lali Dhaba Connectivity. SFM-GA is an approved pipeline project in Bahauddan, Sirsa, Haryana. The site covers 2.5 acres.
Who is building it?
The applicant is Gujarat Gas Limited.
Has it been approved?
Yes. Its status is “Forest land use approved” (since 21 Apr 2026), as of 27 Nov 2026.
Where is it?
In Bahauddan, Sirsa, Haryana.
How big is it?
It has a stated cost of ₹11.1 crore; a site of 2.5 acres and 2.1 acres (0.8 ha) of forest land.
When was it filed?
The application was filed on 6 Mar 2025.
Project details
| Status | Forest land use approved |
|---|---|
| Status since | 21 Apr 2026 |
| Application filed | 6 Mar 2025 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Pipelines |
| Applicant | Gujarat Gas Limited |
| Land area | 2.5 acres (1 ha) |
| Forest land | 2.1 acres (0.8 ha) |
| Project cost | ₹11.1 crore |
| Village / locality | Bahauddan |
| Taluk / tehsil | Sirsa |
| District | Sirsa |
| State | Haryana |
| Location from | Site boundary on record |
| Our reference | WID-HR-02022 |
In context
22 applications in Sirsa since January 2022 are in the same category (Pipelines): 5 approved, 3 filed or under review, and 14 withdrawn, lapsed or rejected. The approved ones took a median of 7 months from filing to approval. At 2.5 acres, this one is larger than 79% of them.
5 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bahauddan, Sirsa, Haryana. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Access to Installation of Weigh Bridge & Service Station Km. 105.172 (R.H.S.)… — lapsed, 2.6 km away
- Diversion of forest land for access to the Proposed Retail Outlet of Bharat… — initial checks, 2.8 km away
- Project by M/s Dream Water World at Mouju Khera — more information requested, 3.4 km away
- Access to Deep Sewak Scrappers — forest land use approved, 4.1 km away
- Access to Deep Computerized Dharam Kanta — lapsed, 4.7 km away
- Creation of 2 phase, 132 KV S/C line on DC Tower with 0.2 Sq. inch ACSR… — in-principle approval, conditions pending, 5 km away
- M/s Narayani Resort on DHS Road to Kotli Road Km 1-2 (RHS) — lapsed, 5.1 km away
- Access to Residential & Commercial Building of M/s Clean Earth Realtors LLP — lapsed, 5.2 km away
More from Gujarat Gas Limited in Sirsa
- Diversion of 0.0969 Ha Forest Land For laying 6" Steel Natural Gas Pipe line… — more information requested
- Diversion of 0.7159 Hectare (7157.77 Sq. Mtr) Forest Land for Laying 125 Mm… — forest land use approved
3 Gujarat Gas projects in Sirsa
All 289 Gujarat Gas projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.