Quick answers
What is Access to 180 KLPD Grain based Ethanol Plant?
Access to 180 KLPD Grain based Ethanol Plant is a lapsed power project in Randauli, Indri, Karnal, Haryana. The site covers 20.8 acres.
Who is building it?
The applicant is Iris Fuel India Private Limited.
Has it been approved?
No. The application was lapsed on 24 Aug 2023, so it is no longer under consideration.
Where is it?
In Randauli, Indri, Karnal, Haryana.
How big is it?
It has a stated cost of ₹5 crore; a site of 20.8 acres and 40 m² of forest land.
When was it filed?
The application was filed on 17 Jan 2023.
Project details
| Official title | access to 180 KLPD Grain based Ethanol Plant along with 4.0 MW Cogeneration Power Plant of IRIS Fuel India Pvt. |
|---|---|
| Status | Lapsed |
| Status since | 24 Aug 2023 |
| Application filed | 17 Jan 2023 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Iris Fuel India Private Limited |
| Land area | 20.8 acres (8.4 ha) |
| Forest land | 40 m² |
| Project cost | ₹5 crore |
| Village / locality | Randauli |
| Taluk / tehsil | Indri |
| District | Karnal |
| State | Haryana |
| Location from | Site boundary on record |
| Our reference | WID-HR-03158 |
In context
16 applications in Karnal since January 2022 are in the same category (Power): 8 approved, 4 filed or under review, and 4 withdrawn, lapsed or rejected. The approved ones took a median of 11 months from filing to approval. At 20.8 acres, this one is larger than 69% of them.
7 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Randauli, Indri, Karnal, Haryana. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- MB FOODS ( industrial unit for Rice Mill ) — forest land use approved, 1.1 km away
- Mb Resort — forest land use approved, 1.6 km away
- Diversion of Forest Land for Connectivity of the Two Roads Nadia to Biana Road… — lapsed, 2.4 km away
- Project by M/s Chaudhary Transport Company — lapsed, 2.6 km away
- Sand Mining Project at Nangal Block Having an Area of 82.85 Ha — environmental approval granted, 4.4 km away
- Sand Mining Project at Nangal Block Having an Area of 82.85 Ha — environmental approval granted, 4.4 km away
- Sand Mining Project at Nangal Block Having an Area of 82.85 Ha — more information requested, 4.4 km away
- Maa Bala Sundri Foods — forest land use approved, 5.2 km away
More from Iris Fuel India Private Limited in Karnal
- Motel With Banquets Hall — lapsed
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.