One of 2 filings for this project. The project's main page, with every filing and where each stands: Expansion of existing 27000 TPA M.S. Ingot unit to 148,500TPA MS Ingot/Billets by…
Project details
| Official title | Expansion of existing 27000 TPA M.S. Ingot unit to 148,500TPA MS Ingot/Billets by installing 3x15T (by replacement of Existing 2x4T Furnace & Addition of 1x15T IF) along with CCM-1x2 strand, 4/7m radius, enhancement of slag crusher capacity from 9,000TPA to 33,000TPA and Production of 145,000TPA Rolled Products by installing 1x25TPH Rolling Mill along with 1x30TPH capacity reheating furnace by M/s Kumardhubi Steels Pvt Ltd at Village: Rajpura, P.O.: Kumardhubi, District: Dhanbad, Jharkhand |
|---|---|
| Status | Cleared for impact study |
| Status since | 15 Aug 2023 |
| Application filed | 15 Aug 2023 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Kumardhubi Steels Private Limited |
| Land area | 5 acres (2 ha) |
| Project cost | ₹48.2 crore |
| Village / locality | Rajpura |
| Taluk / tehsil | Egarkund |
| District | Dhanbad |
| State | Jharkhand |
| Location from | Site boundary on record |
| Our reference | WID-JH-00288 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 20 Aug 2024 | Environmental approval granted | 5 acres | ₹48.2 crore |
| Early planning filed 15 Aug 2023 (this page) | Cleared for impact study | 5 acres | ₹48.2 crore |
In context
13 applications in Dhanbad since January 2022 are in the same category (Industry): 10 approved, 2 filed or under review, and 1 withdrawn, lapsed or rejected. At 5 acres, this one is larger than 62% of them.
Where it is
Rajpura, Egarkund, Dhanbad, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of existing 27000 TPA M.S. Ingot unit to 148,500TPA MS Ingot/Billets… — environmental approval granted, 0 m away
- Proposed Ferro-Alloy Plant by installation of 4x9 MVA Submerged Arc Furnaces… — cleared for impact study, 5.1 km away
- Cluster No. 1 (Group of 7 Mines of ECL) — environmental approval granted, 5.7 km away
- Enhancement of production capacity for Gopinathpur Coal Mine, Mugma Area,… — lapsed, 5.7 km away
- Enhancement of Gopinathpur Mine (Gopinathpur (UG & OC) and Shampur-A (UG & OC)… — lapsed, 6.1 km away
- Enhancement of production capacity of Shampur-A Coal Mine, Mugma Area, Nirsa… — lapsed, 6.6 km away
- Ubchuria Brick Clay Deposit — initial checks, 9.1 km away
- Enhancement of distillery capacity from 500 KLPD to 650 KLPD proposed by M/s.… — initial checks, 12.5 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.