Quick answers
What is this project?
Expansion of the existing 120,000TPA Sponge Iron Plant by installation of Iron Ore Beneficiation Plant 96000 TPA (Throughput), Captive Power Plant 12 MW (AFBC: 4MW & WHRB: 8MW) and installation of 1x9 MVA Submerged Arc Furnace for production of 16,200 TPA Silico Manganese by M/s Shri Balaji Industrial Engineering Ltd at Basti Road, P.O.: Barajamda, District: West Singhbhum, Jharkhand is a proposed industrial project in Bara Jamda, Noamundi, Pashchimi Singhbhum, Jharkhand. The site covers 16.6 acres.
Who is building it?
The applicant is Shri Balaji Industrial Engineering Limited.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 9 Jul 2023), as of 27 Nov 2026.
Where is it?
In Bara Jamda, Noamundi, Pashchimi Singhbhum, Jharkhand.
How big is it?
It has a stated cost of ₹163.5 crore and a site of 16.6 acres.
When was it filed?
The application was filed on 10 Apr 2023.
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 9 Jul 2023 |
| Application filed | 10 Apr 2023 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Shri Balaji Industrial Engineering Limited |
| Land area | 16.6 acres (6.7 ha) |
| Project cost | ₹163.5 crore |
| Village / locality | Bara Jamda |
| Taluk / tehsil | Noamundi |
| District | Pashchimi Singhbhum |
| State | Jharkhand |
| Location from | Site boundary on record |
| Our reference | WID-JH-00508 |
In context
7 applications in Pashchimi Singhbhum since January 2022 are in the same category (Industry): 3 approved, 4 filed or under review, and 0 withdrawn, lapsed or rejected.
6 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bara Jamda, Noamundi, Pashchimi Singhbhum, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Shivans Steel Private Limited-Integrated Greenfield Steel Plant for… — returned to applicant, 750 m away
- Shivans Steel Private Limited-Integrated Greenfield Steel Plant for… — returned to applicant, 750 m away
- Preliminary Exploration (G3) for Manganese and Associated Minerals in Kankura… — forest land use approved, 1.7 km away
- Shivans Steel Private Limited proposes to establish Integrated Greenfield… — cleared for impact study, 2.8 km away
- Silpunji Block — more information requested, 3.5 km away
- Proposed Production of 0.6 Mtpa Rom Ore and Maximum Excavation of 0.299… — under environmental review, 3.6 km away
- Amendment in Environmental Clearance granted to Noamundi Iron Mine of Tata… — environmental approval granted, 6.1 km away
- Environment Clearance of Noamundi Iron Mine of Tata Steel Limited — returned to applicant, 6.2 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.