Quick answers
What is this project?
Expansion of Gajanan Ferro Pvt. Ltd. for enhancement of Ferro Alloys production from 26,400 to 112,000 TPA (max.) with change in product mix, Installation of 2x900 TPD DRI unit for Production of 594000 TPA Sponge Iron, Captive Power Plant for 76 MW power generation, 158,000 TPA Chrome Ore Briquette Plant is a proposed industrial project in Jorshol, Dhalbhumgarh, Purbi Singhbhum, Jharkhand. The site covers 67.8 acres.
Who is building it?
The applicant is Gajanan Ferro Private Limited.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 18 Aug 2024), as of 27 Nov 2026.
Where is it?
In Jorshol, Dhalbhumgarh, Purbi Singhbhum, Jharkhand.
How big is it?
It has a stated cost of ₹349.3 crore and a site of 67.8 acres.
When was it filed?
The application was filed on 7 Mar 2024.
One of 2 filings for this project. The project's main page, with every filing and where each stands: Expansion of Gajanan Ferro Pvt. Ltd. for enhancement of Ferro Alloys production from…
Project details
| Official title | Expansion of Gajanan Ferro Pvt. Ltd. for enhancement of Ferro Alloys production from 26,400 to 112,000 TPA (max.) with change in product mix, Installation of 2x900 TPD DRI unit for Production of 594000 TPA Sponge Iron, Captive Power Plant for 76 MW power generation, 158,000 TPA Chrome Ore Briquette Plant, along with 20 TPH Jigging Plant at Village: Kadambeda, P.S.: Dhalbhumgarh, District- East Singhbhum, Jharkhand State |
|---|---|
| Status | Cleared for impact study |
| Status since | 18 Aug 2024 |
| Application filed | 7 Mar 2024 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Gajanan Ferro Private Limited |
| Land area | 67.8 acres (27.4 ha) |
| Project cost | ₹349.3 crore |
| Village / locality | Jorshol |
| Taluk / tehsil | Dhalbhumgarh |
| District | Purbi Singhbhum |
| State | Jharkhand |
| Location from | Site boundary on record |
| Our reference | WID-JH-00835 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 10 Jan 2025 | Environmental approval granted | 67.8 acres | ₹349.3 crore |
| Early planning filed 7 Mar 2024 (this page) | Cleared for impact study | 67.8 acres | ₹349.3 crore |
In context
25 applications in Purbi Singhbhum since January 2022 are in the same category (Industry): 17 approved, 4 filed or under review, and 4 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 67.8 acres, this one is smaller than 60% of them.
9 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Jorshol, Dhalbhumgarh, Purbi Singhbhum, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of Gajanan Ferro Pvt. Ltd. for enhancement of Ferro Alloys… — environmental approval granted, 0 m away
- Proposed Enhancement of Ferro Alloys Plant from 26400 to 179000 TPA(Max) with… — cleared for impact study, 0 m away
- Change in the product mix for inclusion of Ferro-Chrome of 26,400TPA (or)… — initial checks, 100 m away
- Expansion of existing plant by enhancing Ferro Alloy plant from 0.112 to 0.266… — environmental approval granted, 300 m away
- Expansion of existing plant by enhancing Ferro Alloy plant from 0.112 to 0.266… — cleared for impact study, 300 m away
- Expansion of existing plant - Pellet Plant, Power Plant & Briquet Plant — lapsed, 350 m away
- 132 kV D/C Surda-Bahragora Transmission Line — lapsed, 4.1 km away
- Expansion of Paper Mill and Power Generation From Process Steam for Stark… — lapsed, 4.4 km away
More from Gajanan Ferro Private Limited in Purbi Singhbhum
- Expansion of existing plant by enhancing Ferro Alloy plant from 0.112 to 0.266… — environmental approval granted
- Expansion of existing plant by enhancing Ferro Alloy plant from 0.112 to 0.266… — cleared for impact study
- Expansion of existing plant - Pellet Plant, Power Plant & Briquet Plant — lapsed
- Change in the product mix for inclusion of Ferro-Chrome of 26,400TPA (or)… — initial checks
- Proposed Enhancement of Ferro Alloys Plant from 26400 to 179000 TPA(Max) with… — cleared for impact study