Project details
| Official title | North Dhadu ( Western Part ) Open Cast Coal Mine of 4.5 MTPA capacity in an area of 714.54 Ha of M/s. NLC India Limited in Latehar district of Jharkhand State |
|---|---|
| Status | Cleared for impact study |
| Status since | 15 Apr 2026 |
| Application filed | 16 Dec 2025 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Mining |
| Applicant | Nlcil |
| Land area | 1,765.7 acres (714.5 ha) |
| Project cost | ₹1,354.2 crore |
| Village / locality | Hempur |
| Taluk / tehsil | Balumath |
| District | Latehar |
| State | Jharkhand |
| Location from | Site boundary on record |
| Our reference | WID-JH-01160 |
In context
76 applications in Latehar since January 2022 are in the same category (Mining): 47 approved, 17 filed or under review, and 12 withdrawn, lapsed or rejected. The approved ones took a median of 43 days from filing to approval. At 1,765.7 acres, this one is larger than 80% of them.
No other mining lease on record is within 500 m of this site; 3 have applied within 5 km.
Where it is
Hempur, Balumath, Latehar, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- North Dhadu ( Western Part ) Open Cast Coal Mine of 4.5 MTPA capacity in an… — under forest review, 0 m away
- North Dhadu Eastern Part Coal Mining Project — withdrawn, 2.9 km away
- North Dhadu (Eastern Part) Coal Mine Project with project area :546.59 HA,… — more information requested, 3.1 km away
- North Dhadu (Eastern Part) Coal Mine Project with project area :546.59 HA,… — cleared for impact study, 3.1 km away
- North Dhadu Eastern Part Coal Mining Project — under forest review, 3.1 km away
- North Dhadu (Eastern Part) Coal Mining Project — returned to applicant, 3.2 km away
- Chakla Opencast Coal Mine (North Karanpura Coalfield) (ML Area: 863 ha) with… — environmental approval granted, 5.1 km away
- Brick Soil Mining for M/s Kita Bricks — under environmental review, 8.8 km away
More from Nlcil in Latehar
- North Dhadu ( Western Part ) Open Cast Coal Mine of 4.5 MTPA capacity in an… — under forest review
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.