What is Cluster X Coal Mining Project and Coal Washery?
Cluster X Coal Mining Project and Coal Washery is an approved mining project in Banshara, Chandankiyari, Bokaro, Jharkhand. The site covers 4,127.9 acres.
Who is building it?
The applicant is Bharat Coking Coal Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 22 Apr 2026), as of 27 Nov 2026.
Where is it?
In Banshara, Chandankiyari, Bokaro, Jharkhand.
How big is it?
It has a stated cost of ₹154.7 crore and a site of 4,127.9 acres.
When was it filed?
The application was filed on 7 Feb 2025.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 22 Apr 2026 |
| Application filed | 7 Feb 2025 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Mining |
| Applicant | Bharat Coking Coal Limited |
| Land area | 4,127.9 acres (1,670.5 ha) |
| Project cost | ₹154.7 crore |
| Village / locality | Banshara |
| Taluk / tehsil | Chandankiyari |
| District | Bokaro |
| State | Jharkhand |
| Location from | Site boundary on record |
| Our reference | WID-JH-01337 |
In context
93 applications in Bokaro since January 2022 are in the same category (Mining): 76 approved, 3 filed or under review, and 14 withdrawn, lapsed or rejected. The approved ones took a median of 41 days from filing to approval. At 4,127.9 acres, this one is larger than 98% of them.
No other mining lease on record is within 500 m of this site; 1 has applied within 5 km.
Where it is
Banshara, Chandankiyari, Bokaro, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Sitanala Coal Mine — environmental approval granted, 1.2 km away
- Sitanala Coal Mine — lapsed, 1.2 km away
- Sitanala Coal Mine — lapsed, 1.2 km away
- LILO of 132 KV Chandankyari - Govindpur Transmission Line at Putki — in-principle approval, conditions pending, 3.1 km away
- Parbatpur Centeral Coal Block — environmental approval granted, 7 km away
- Parbatpur Central Coal Block — not approved, 7 km away
- Industrial project by ESL Steel Limited (Formerly known as Electrosteel Steels… — in-principle approval, conditions pending, 12.7 km away
- Surjyadi Stone Mine — environmental approval granted, 13 km away