What is Developing? Open the mapMap

WithdrawnMining · Pakur, Jharkhand

Bhuska Stone Mine

Bhuska Stone Mine is a withdrawn mining project in Bhusko, Pakaur, Pakur, Jharkhand. The site covers 5.4 acres. Its stated project cost is ₹1.4 crore. As of 27 Nov 2026, its status is “Withdrawn” (since 7 Oct 2025).

See it on the live map All projects in Pakur

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is Bhuska Stone Mine?

Bhuska Stone Mine is a withdrawn mining project in Bhusko, Pakaur, Pakur, Jharkhand. The site covers 5.4 acres.

Who is building it?

The applicant is Shri Dinesh Tanwani.

Has it been approved?

No. The application was withdrawn on 7 Oct 2025, so it is no longer under consideration.

Where is it?

In Bhusko, Pakaur, Pakur, Jharkhand.

How big is it?

It has a stated cost of ₹1.4 crore and a site of 5.4 acres.

When was it filed?

The application was filed on 7 Oct 2025.

One of 3 filings for this project. The project's main page, with every filing and where each stands: Bhuska Stone Mine

Project details

StatusWithdrawn
Status since7 Oct 2025
Application filed7 Oct 2025
Approval soughtEnvironmental approval
Application typeNew project
SectorMining
ApplicantShri Dinesh Tanwani
Land area5.4 acres (2.2 ha)
Project cost₹1.4 crore
Village / localityBhusko
Taluk / tehsilPakaur
DistrictPakur
StateJharkhand
Location fromSite boundary on record
Our referenceWID-JH-01522

All filings for this project

This project has 3 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
New project filed 24 Oct 2025Environmental approval granted5.4 acres₹1.4 crore
New project filed 7 Oct 2025 (this page)Withdrawn5.4 acres₹1.4 crore
Early planning filed 21 Oct 2024Cleared for impact study5.4 acres₹1.4 crore

In context

209 applications in Pakur since January 2022 are in the same category (Mining): 189 approved, 5 filed or under review, and 15 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 5.4 acres, this one is smaller than 71% of them.

2 other mining leases have applied within 500 m of this site; together with this one they cover 16.6 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 30 mining leases have applied within 5 km.

Where it is

Bhusko, Pakaur, Pakur, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.