Quick answers
What is this project?
Change in Product Mix (Under Para 7(ii)(a) of EIA Notification 2006) for inclusion of Wires (Sizes - 0.8 mm to 25 mm) by installation of 0.228 MTPA Wire Drawing Unit for processing of Wire Rods without change in existing production capacity of 1.6 MTPA of existing Rolling Mills is a lapsed industrial project in Kusiara, Patratu, Ramgarh, Jharkhand. The site covers 551.5 acres.
Who is building it?
The applicant is Jindal Steel Limited.
Has it been approved?
No. The application was lapsed on 18 May 2026, so it is no longer under consideration.
Where is it?
In Kusiara, Patratu, Ramgarh, Jharkhand.
How big is it?
It has a stated cost of ₹26.3 crore and a site of 551.5 acres.
When was it filed?
The application was filed on 1 Oct 2025.
Project details
| Official title | Change in Product Mix (Under Para 7(ii)(a) of EIA Notification 2006) for inclusion of Wires (Sizes - 0.8 mm to 25 mm) by installation of 0.228 MTPA Wire Drawing Unit for processing of Wire Rods without change in existing production capacity of 1.6 MTPA of existing Rolling Mills Located at Village Balkudra, Block Patratu, District Ramgarh, State Jharkhand by M/s. Jindal Steel and Power Limited |
|---|---|
| Status | Lapsed |
| Status since | 18 May 2026 |
| Application filed | 1 Oct 2025 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Industry |
| Applicant | Jindal Steel Limited |
| Land area | 551.5 acres (223.2 ha) |
| Project cost | ₹26.3 crore |
| Village / locality | Kusiara |
| Taluk / tehsil | Patratu |
| District | Ramgarh |
| State | Jharkhand |
| Location from | Site area on record |
| Our reference | WID-JH-01797 |
In context
30 applications in Ramgarh since January 2022 are in the same category (Industry): 12 approved, 10 filed or under review, and 8 withdrawn, lapsed or rejected. The approved ones took a median of 31 days from filing to approval. At 551.5 acres, this one is larger than 93% of them.
9 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kusiara, Patratu, Ramgarh, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Transfer of Environmental Clearance (EC) dated 22.09.2008 & EC amendment dated… — more information requested, 150 m away
- Diversion of Forest Land for Shifting/Diversion of 132 KV Patratu -… — lapsed, 1.6 km away
- Project by Patratu Vidyut Utpadan Nigam Limited — in-principle approval, conditions pending, 2.1 km away
- PATRATU VIDYUT UTPADAN NIGAM LIMITED_Ash Corridor — in-principle approval, conditions pending, 2.7 km away
- 3 x 800 MW (Phase-I) Patratu Super Thermal Power Project at Patratu, District… — under environmental review, 3.2 km away
- 3 x 800 MW (Phase-I) Patratu Super Thermal Power Project at Patratu, District… — returned to applicant, 3.5 km away
- 3 x 800 MW (Phase-I) Patratu Super Thermal Power Project at Patratu, District… — returned to applicant, 3.7 km away
- 3 x 800 MW (Phase-I) Patratu Super Thermal Power Project — environmental approval granted, 3.7 km away
More from Jindal Steel Limited in Ramgarh
- Transfer of Environmental Clearance (EC) dated 22.09.2008 & EC amendment dated… — more information requested
All 39 Jindal Steel projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.