| Status | Lapsed |
|---|---|
| Status since | 23 Nov 2026 |
| Application filed | 31 Jul 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Public facilities |
| Applicant | Birla Institute of Technology |
| Land area | 567.3 acres (229.6 ha) |
| Forest land | 402.9 acres (163.1 ha) |
| Project cost | ₹15.8 crore |
| Village / locality | Mesra |
| Taluk / tehsil | Kanke |
| District | Ranchi |
| State | Jharkhand |
| Location from | Site boundary on record |
| Our reference | WID-JH-02397 |
In context
3 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Mesra, Kanke, Ranchi, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed excavation of 1200 cum/year Bricks clay from Sugnu Bricks Soil Mining… — environmental approval granted, 1.5 km away
- Proposed excavation of 1200 cum/year Bricks clay from Sugnu Brick Soil Mining… — environmental approval granted, 1.6 km away
- Samriddhi Heights — environmental approval granted, 3.4 km away
- Shifting of 220 KV Gola- Ranchi transmission line from the premises of Khijree… — in-principle approval, conditions pending, 5 km away
- Expansion of Residential Complex "Diamond City" — environmental approval granted, 5.7 km away
- Expansion of Residential Complex Diamond City — lapsed, 5.7 km away
- Proposed Affordable Housing Project "The Habitat" — more information requested, 7 km away
- Proposed Residential building "Highland Park" — environmental approval granted, 7.6 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.