What is 400KV D/C Quad Moose Katia-Puvnl(Patratu) Transmission Line?
400KV D/C Quad Moose Katia-Puvnl(Patratu) Transmission Line is an approved power project in Bartua, Patratu, Ramgarh, Jharkhand. The site covers 3,614.4 acres.
Who is building it?
The applicant is Jharkhand Urja Sancharan Nigam Limited.
Has it been approved?
Yes. Its status is “Forest land use approved” (since 21 Mar 2025), as of 27 Nov 2026.
Where is it?
In Bartua, Patratu, Ramgarh, Jharkhand.
How big is it?
It has a stated cost of ₹42.7 crore; a site of 3,614.4 acres and 36.9 acres (15 ha) of forest land.
When was it filed?
The application was filed on 5 Nov 2023.
Project details
| Status | Forest land use approved |
|---|---|
| Status since | 21 Mar 2025 |
| Application filed | 5 Nov 2023 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Jharkhand Urja Sancharan Nigam Limited |
| Land area | 3,614.4 acres (1,462.7 ha) |
| Forest land | 36.9 acres (15 ha) |
| Project cost | ₹42.7 crore |
| Village / locality | Bartua |
| Taluk / tehsil | Patratu |
| District | Ramgarh |
| State | Jharkhand |
| Location from | Site boundary on record |
| Our reference | WID-JH-02579 |
In context
13 applications in Ramgarh since January 2022 are in the same category (Power): 3 approved, 6 filed or under review, and 4 withdrawn, lapsed or rejected. At 3,614.4 acres, this one is larger than 75% of them.
13 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bartua, Patratu, Ramgarh, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Transfer of Environment Clearance MoEF&CC /SEIAA File No. F.… — lapsed, 1.9 km away
- Expansion in Cement Production Capacity from 0.528 Million TPA to 4.6 Million… — environmental approval granted, 2 km away
- Expansion in Cement Production Capacity from 0.528 Million TPA to 4.6 Million… — cleared for impact study, 2 km away
- Transfer of Environment Clearance MoEF&CC /SEIAA File No. F.… — environmental approval granted, 2 km away
- Expansion in Cement Production Capacity from 0.528 Million TPA to 4.6 Million… — under environmental review, 2 km away
- Expansion in Cement Production Capacity from 0.528 Million TPA to 4.6 Million… — lapsed, 2 km away
- 3 x 800 MW (Phase-I) Patratu Super Thermal Power Project — environmental approval granted, 2.1 km away
- 3 x 800 MW (Phase-I) Patratu Super Thermal Power Project at Patratu, District… — returned to applicant, 2.1 km away
More from Jharkhand Urja Sancharan Nigam Limited in Ramgarh
- 132 KV D/C Gola Silli Transmission Line — under forest review