Cleared for impact studyIndustry · Yadgir, Karnataka

Agrochemicals –Pesticides (Technical) & Intermediates, Speciality Chemicals Manufacturing Industry with production capacity of 12050 MTA

Agrochemicals –Pesticides (Technical) & Intermediates, Speciality Chemicals Manufacturing Industry with production capacity of 12050 MTA is a proposed industrial project in Kadechur, Yadgir, Karnataka. The site covers 10 acres. Its stated project cost is ₹70 crore. As of 27 Nov 2026, its status is “Cleared for impact study” (since 7 Nov 2022).

See it on the live map All projects in Yadgir

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

One of 2 filings for this project. The project's main page, with every filing and where each stands: Agrochemicals –Pesticides (Technical) & Intermediates, Speciality Chemicals…

Project details

Official titleProposed Establishment of Agrochemicals –Pesticides (Technical) & Intermediates, Speciality Chemicals Manufacturing Industry with production capacity of 12050 MTA along With R & D Products And 2 MW Captive Power Plant
StatusCleared for impact study
Status since7 Nov 2022
Application filed7 Nov 2022
Approval soughtEnvironmental approval
Application typeEarly planning
SectorIndustry
ApplicantMeenakshi Agro Chemicals
Land area10 acres (4 ha)
Project cost₹70 crore
Village / localityKadechur
Taluk / tehsilYadgir
DistrictYadgir
StateKarnataka
Location fromSite boundary on record
Our referenceWID-KA-00167

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
New project filed 12 Jun 2023Environmental approval granted10 acres₹70 crore
Early planning filed 7 Nov 2022 (this page)Cleared for impact study10 acres₹70 crore

In context

94 applications in Yadgir since January 2022 are in the same category (Industry): 73 approved, 13 filed or under review, and 8 withdrawn, lapsed or rejected. The approved ones took a median of 23 days from filing to approval. At 10 acres, this one is larger than 80% of them.

87 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Kadechur, Yadgir, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.