Quick answers
What is this project?
Sugar Plant (5000 TCD), Co-generation Plant (25MW) and Molasses based Distillery (45 KLPD) by M/s M S Patil Sugars Ltd is a lapsed industrial project in Nimbal [B.K.], Indi, Vijayapura, Karnataka. The site covers 0.1 acres.
Who is building it?
The applicant is M S Patil Sugars Limited.
Has it been approved?
No. The application was lapsed on 29 Oct 2024, so it is no longer under consideration.
Where is it?
In Nimbal [B.K.], Indi, Vijayapura, Karnataka.
How big is it?
It has a site of 0.1 acres.
When was it filed?
The application was filed on 31 Jul 2023.
Project details
| Official title | Sugar Plant (5000 TCD), Co-generation Plant (25MW) and Molasses based Distillery (45 KLPD) at Village Nimbal, (BK), Tehsil Indi, District Bijapur, Karnataka by M/s M S Patil Sugars Ltd |
|---|---|
| Status | Lapsed |
| Status since | 29 Oct 2024 |
| Application filed | 31 Jul 2023 |
| Approval sought | Environmental approval |
| Application type | Validity extension |
| Sector | Industry |
| Applicant | M S Patil Sugars Limited |
| Land area | 600 m² |
| Village / locality | Nimbal [B.K.] |
| Taluk / tehsil | Indi |
| District | Vijayapura |
| State | Karnataka |
| Location from | Site boundary on record |
| Our reference | WID-KA-00437 |
In context
37 applications in Vijayapura since January 2022 are in the same category (Industry): 20 approved, 8 filed or under review, and 9 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 0.1 acres, this one is smaller than 100% of them.
2 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Nimbal [B.K.], Indi, Vijayapura, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- 4500 TCD Sugar Unit, 24 MW Co-generation Unit and 200 KLPD Multi feed… — environmental approval granted, 4.6 km away
- 4500 TCD Sugar Unit, 24 MW Co-generation Unit and 200 KLPD Multi feed… — cleared for impact study, 4.6 km away
- Building Stone Quarry — environmental approval granted, 12.5 km away
- "Building Stone Quarry" — environmental approval granted, 12.5 km away
- Building Stone Quarry of Sri. Shivanagouda B Patil — environmental approval granted, 14.5 km away
- Building Stone Quarry of Sri Kasimsab M Girganvi — environmental approval granted, 19.4 km away
- Sugar Cane Crushing plant Capacity of 5000 TCD, Cogeneration Plant 30 MW & B-… — returned to applicant, 19.5 km away
- Sugar Cane Crushing plant Capacity of 5000 TCD, Cogeneration Plant 30 MW & B-… — returned to applicant, 19.5 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.